20 OCTGSTR-3B · Summary return · Sep 2026in 4 days 21 OCTTax Audit Report · Form 3CA/3CB · AY 2026-27 · extended from 30 Sepin 5 days 30 OCTAOC-4 · Financial statements · FY 2025-26in 14 days 7 NOVTDS / TCS deposit · Deducted in Oct 2026in 22 days 11 NOVGSTR-1 · Outward supplies · Oct 2026in 26 days 15 NOVPF & ESI · Contributions · Oct 2026in 30 days 21 NOVITR filing · Audit cases · AY 2026-27 · extended from 31 Octin 36 days 29 NOVMGT-7 / 7A · Annual return · FY 2025-26in 44 days
All due dates

AS 7, Construction Contracts: fixed price and cost plus contracts, contract revenue and costs, the percentage of completion method, expected losses and disclosures

When the outcome of a contract can be estimated reliably, revenue and costs are recognised by reference to the stage of completion at the reporting date (paragraph 21). When it is...

Published
Updated
Reading time
8 min
Views
19
Questions
6 answered
  • Expert Reviewed
  • Medium Complexity
  • In-Depth Guide
Topic
Accounting Standards & Bookkeeping
Published
October 4, 2026
Last updated
Oct 4, 2026
Reading time
8 min
0:00
Last updated: October 2026Verified against: Government sources

AS 7 tells a contractor how to record revenue, cost and profit on a contract that runs across more than one year. Revenue and cost are recognised as the work is done, not when the contract is finished and not when the customer pays, and a loss on the whole contract is recognised the moment it is expected. The standard is for contractors and applies to roads, buildings, plant and similar work. The accounts built on it are part of the work of our books of accounts and compliance team for contractors.

Accounting Standards as on 1 April 2025 (ICAI compendium), read with the Companies (Accounting Standards) Rules, 2021 as amended up to G.S.R. 169(E) of 10 March 2026. Later amendments should be checked on icai.org and mca.gov.in. Companies on Ind AS follow Ind AS 115; see our Ind AS 115 guide. A real estate developer selling its own units should check which guidance applies, as paragraph 1 applies the standard to contractors.

What the standard requires

ParagraphsWhat it requiresWhat it means in the books
2.2, 2.3A fixed price contract agrees a fixed price or a fixed rate per unit; a cost plus contract reimburses allowable costs plus a percentage or fixed feeClassify the contract first
6-9Apply the standard to each contract; treat the separately negotiated assets in one contract separately, and a package of closely related contracts togetherDecide the unit of account
10-14Revenue is the agreed amount plus variations, claims and incentives, to the extent probable and measurableDo not book claims until negotiations are advanced
15-20Costs include those directly related to the contract, those allocable to contract activity in general, and those chargeable to the customer; general administration and selling costs not reimbursed are excludedKeep a cost sheet for each contract
21, 22, 23Fixed price: four conditions for reliable estimate; cost plus: two conditionsTest before using percentage of completion
29, 30Stage of completion by costs to total cost, by survey or by physical proportion; costs for future activity, such as materials not yet used, are excluded from costs incurredCost method uses work-done costs only
31-34If the outcome cannot be estimated reliably, revenue equals recoverable costs incurred and no profitRevert to paragraph 21 once the uncertainty goes
35, 36Expected loss is recognised at once, regardless of stage or profit on other contractsProvide for the whole loss
41-43Present the gross amount due from customers as an asset and the gross amount due to customers as a liabilityNet by contract

Method

  1. Fix revenue (agreed price plus probable, measurable variations) and estimate total cost.
  2. Compute the stage of completion: costs incurred for work done to date divided by total estimated cost.
  3. Cumulative revenue is that percentage of total revenue; revenue for the year is the cumulative figure less revenue of earlier years.
  4. Costs of the year are normally recognised as incurred.
  5. Re-estimate at each year end; the percentage is applied to the current estimates on a cumulative basis (paragraph 37).
  6. If total estimated cost now exceeds total revenue, recognise the whole loss at once.
  7. Present the amount due from or to customers.

Worked example: Naresh Infra Works, a road contract

The entity and all figures in this example are invented for illustration.

Naresh Infra Works signs a fixed price road contract for 50,00,000 on 1 April. All costs incurred relate to work done. Progress billings are 14,00,000 in year 1, 11,00,000 in year 2 and 25,00,000 in year 3.

WorkingYear 1Year 2Year 3
Cost incurred in the year12,00,00016,00,00028,00,000
Cumulative cost incurred12,00,00028,00,00056,00,000
Estimated cost to complete28,00,00028,00,000nil
Estimated total cost40,00,00056,00,00056,00,000
Stage of completion (cumulative cost / total cost)30 per cent50 per cent100 per cent
Cumulative revenue (stage x 50,00,000)15,00,00025,00,00050,00,000
Revenue for the year15,00,00010,00,00025,00,000
Cost recognised in the year12,00,00016,00,00028,00,000
Profit or (loss) before provision3,00,000(6,00,000)(3,00,000)

In year 1 the estimated total cost of 40,00,000 is below the price, so a profit of 10,00,000 is expected and 30 per cent of it, 3,00,000, is recognised. In year 2 the estimate rises to 56,00,000, a cost overrun, so the contract is now expected to lose 6,00,000 (50,00,000 less 56,00,000). Under paragraphs 35 and 36 the whole loss is recognised now, whatever the stage.

Provision in year 2. Cumulative result before the provision: 3,00,000 profit in year 1 less 6,00,000 loss in year 2 = a loss of 3,00,000 to date. The whole expected loss is 6,00,000, so a provision of 3,00,000 is made to bring the cumulative loss to 6,00,000.

YearEntryDebitCredit
2Contract costs (expense) Dr3,00,000
To Provision for expected loss on contract3,00,000
3Provision for expected loss on contract Dr3,00,000
To Contract costs (expense)3,00,000
Result for the yearYear 1Year 2Year 3Total
Profit or (loss) before provision3,00,000(6,00,000)(3,00,000)(6,00,000)
Provision created or (released)nil(3,00,000)3,00,000nil
Net profit or (loss)3,00,000(9,00,000)nil(6,00,000)

Amount due from or to customers (paragraphs 42 and 43).

At the end ofCosts incurred plus recognised profits less recognised lossesProgress billings (cumulative)Gross amount due from or (to) customers
Year 112,00,000 + 3,00,000 = 15,00,00014,00,0001,00,000 from customers
Year 228,00,000 + 3,00,000 - 9,00,000 = 22,00,00025,00,000(3,00,000) to customers
Year 356,00,000 - 6,00,000 = 50,00,00050,00,000nil

Check. Total revenue 15,00,000 + 10,00,000 + 25,00,000 = 50,00,000, the contract price. Total cost 12,00,000 + 16,00,000 + 28,00,000 = 56,00,000. The net result over three years, 3,00,000 - 9,00,000 + nil = a loss of 6,00,000 = 50,00,000 - 56,00,000. At the end of year 2 the amount due to customers of 3,00,000 equals the provision, since revenue recognised equals billings (25,00,000).

Disclosure

ParagraphDisclosure
38Contract revenue recognised in the period, the methods used to determine it and the methods used to determine the stage of completion
39, 40For contracts in progress: aggregate costs incurred and recognised profits (less recognised losses), advances received and retentions
41-43Gross amount due from customers as an asset; gross amount due to customers as a liability
44Contingencies, such as warranty costs and penalties, under AS 4

Retentions are billed amounts withheld until conditions are satisfied or defects rectified; advances are amounts received before the work is done (paragraph 40). For contingencies see our guide to AS 4; for revenue generally, AS 9.

Common mistakes

  • Taking revenue when bills are raised instead of by the stage of completion; billing does not show the work done (paragraph 29).
  • Including materials delivered to site but not yet used in costs incurred when the stage is measured by cost (paragraph 30).
  • Recognising an expected loss only in proportion to the work done, rather than in full at once.
  • Booking a claim as revenue before negotiations are advanced and the amount is probable (paragraph 13).

Need help with contract accounting?

If you are a contractor and need contract-wise revenue, cost sheets and the amount due from customers worked out, our team can set up the records and prepare the accounts. See our books of accounts and compliance service and send us your contracts and cost records.

Key takeaways

  • Recognise contract revenue and costs by the stage of completion when the outcome can be estimated reliably.
  • A fixed price contract needs four conditions for a reliable estimate; a cost plus contract needs two.
  • An expected loss is recognised in full and immediately.
  • Revised estimates apply on a cumulative basis.
  • Present the amount due from or to customers, with the disclosures in paragraphs 38 to 44.

Read next

Disclaimer: Based on the Accounting Standards issued by the Institute of Chartered Accountants of India as on 1 April 2025, the Companies (Accounting Standards) Rules, 2021 as amended up to G.S.R. 169(E) of 10 March 2026, the Companies Act, 2013 and the ICAI guidance named in the article, as consulted on 4 October 2026. The worked example uses invented figures. Later amendments should be checked on icai.org and mca.gov.in. This article is general information, not legal advice; check the official text before acting.

Quick recapKey facts & short answers

Key Facts About AS 7 Construction Contracts

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

What is a fixed price contract?

One where the contractor agrees a fixed contract price, or a fixed rate per unit of output, sometimes with escalation clauses (paragraph 2.2).

How is the stage of completion measured?

By cost incurred to estimated total cost, by surveys of work performed, or by completion of a physical proportion; use the method that measures work performed reliably (paragraph 29).

Know which registrations your business actually needs — both too few and too many cost money.

— TaxClue Compliance Desk

AS 7 Construction Contracts: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related Services & Guides

Was this article helpful?
About the author
13,350 articles
Vikas Sharma Verified expert Tax & Compliance Expert

Experienced in company registration, GST, trademark, and compliance. Helping Indian businesses stay compliant.

Last reviewed: Live

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case — always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 6 questions readers ask most on this topic.

One where the contractor agrees a fixed contract price, or a fixed rate per unit of output, sometimes with escalation clauses (paragraph 2.2).

By cost incurred to estimated total cost, by surveys of work performed, or by completion of a physical proportion; use the method that measures work performed reliably (paragraph 29).

As soon as it is probable that total contract costs will exceed total contract revenue, in full and irrespective of the stage (paragraphs 35 and 36).

Revenue is recognised only to the extent of recoverable costs incurred, and no profit is recognised (paragraphs 31 and 32).

Variations when the customer's approval is probable and the amount measurable; claims only once negotiations are at an advanced stage (paragraphs 12 and 13).

The standard applies to contractors (paragraph 1); a developer should check which guidance fits its transactions.