Next due
11 OCTGSTR-1 · Outward supplies · Sep 2026in 3 days 15 OCTPF & ESI · Contributions · Sep 2026in 7 days 20 OCTGSTR-3B · Summary return · Sep 2026in 12 days 21 OCTTax Audit Report · Form 3CA/3CB · AY 2026-27 · extended from 30 Sepin 13 days 30 OCTAOC-4 · Financial statements · FY 2025-26in 22 days 7 NOVTDS / TCS deposit · Deducted in Oct 2026in 30 days 21 NOVITR filing · Audit cases · AY 2026-27 · extended from 31 Octin 44 days 29 NOVMGT-7 / 7A · Annual return · FY 2025-26in 52 days
All due dates

Project cost, means of finance and the feasibility study for a new unit: what goes into each, how they tie together, and the viability tests, with a worked example for a food-processing unit

Project cost is the total of land, building, plant, installation, pre-operative expenses, a contingency and the margin money for working capital. Means of finance is the list of...

Published
Updated
Reading time
7 min
Views
11
Questions
7 answered
  • Expert Reviewed
  • Medium Complexity
Topic
Accounting Standards & Bookkeeping
Published
October 6, 2026
Last updated
Oct 7, 2026
Reading time
7 min
0:00
Last updated: October 2026Verified against: Government sources

Before money is raised for a new unit, two statements have to agree: what the project will cost, and where each rupee of that cost will come from. Around them sits the feasibility study, which asks whether the unit should be built at all. A promoter who prepares these three with care gets a cleaner loan discussion and fewer surprises when the building is half complete.

The heads of project cost

Project cost is built head by head from quotations and estimates, not from a round figure.

HeadWhat it covers
Land and site developmentPurchase or lease premium, levelling, boundary, approach road
Building and civil worksFactory shed, store, office, drainage, with architect's fees
Plant and machineryPrice of equipment, freight, taxes not recoverable, erection and trial
Electrical, installation and utilitiesPower connection, transformer, water, effluent handling
Furniture, laboratory and office equipmentSmaller items needed before the first day
Pre-operative expensesRegistration, licences, consultants, staff training, trial run, interest during construction
ContingencyA cushion for price rises and omissions
Margin money for working capitalThe part of the first working capital cycle the promoter must fund

Be careful with two items. Interest during construction is a real cost of the project and belongs in the pre-operative head. Margin money is not an expense; it is the long-term money that sits in stock and receivables once the unit runs.

The means of finance and why it must equal the cost

Every rupee of cost needs a source: promoter equity (share capital, or capital in a partnership or LLP), a term loan, unsecured loans from promoters or friends (often placed behind the lender's claim), and sometimes a subsidy. If the sources total less than the cost, the unit is half funded; if more, the plan is padded. Government schemes change from time to time, so treat any support as an item to be confirmed; see our posts on CGTMSE and SIDBI schemes. Banks follow their regulator's directions and their own credit policy, which are not covered here.

If you are preparing the funding side of a new project, our project funding service is built around exactly these two statements.

The feasibility study in four parts

PartQuestionTypical evidence
TechnicalCan the unit make the product at the planned quality and volume?Machine specifications, layout, raw material sources, power and water, skilled staff
CommercialWill customers buy at the assumed price and volume?Customer enquiries, price lists, competitor offers, a sales ramp-up
FinancialDoes the project earn enough to repay and reward the promoter?Projected statements, break-even, payback, repayment ratios
Legal and regulatoryAre approvals, licences and title in order?Title documents, approvals, environmental and food licences, agreements

Worked example: a ready-mix food-processing unit

Invented facts, all assumed: a promoter plans a unit making packaged ready-mix flours. Amounts are in ₹ lakh, rounded to two decimals unless stated.

Step 1: project cost.

Head₹ lakh
Land and site development35.00
Building and civil works60.00
Plant and machinery120.00
Electrical, installation and utilities15.00
Furniture, laboratory and office equipment5.00
Pre-operative expenses (including interest during construction)10.00
Contingency at an assumed 5 per cent of building, plant, electrical and furniture heads (200.00)10.00
Margin money for working capital25.00
Total project cost280.00

Check: 35 + 60 + 120 + 15 + 5 = 235; plus 10 = 245; plus 10 = 255; plus 25 = 280.

Step 2: means of finance.

Source₹ lakh
Promoter equity85.00
Promoter unsecured loan15.00
Term loan (assumed 10 per cent interest)170.00
Capital subsidy (assumed; if it arrives after the last payment, a bridge is needed)10.00
Total means of finance280.00

Check: 85 + 15 + 170 + 10 = 280, equal to the project cost. Term loan to promoter equity = 170 ÷ 85 = 2.00 (a figure for this example, not a norm).

Step 3: break-even. Assumed full capacity is 1,500 tonnes a year at ₹2.00 lakh a tonne; variable cost (ingredients, packing, power, freight) is ₹1.80 lakh a tonne, so contribution = 2.00 − 1.80 = 0.20 per tonne. Fixed costs: 90.00 cash costs plus 30.00 depreciation = 120.00; interest in the first year = 10% × 170.00 = 17.00. Total fixed charges = 137.00.

Break-even = fixed charges ÷ contribution per tonne = 137.00 ÷ 0.20 = 685 tonnes, which is 685 ÷ 1,500 = 45.7 per cent of capacity. Cash break-even excludes depreciation: (137.00 − 30.00) ÷ 0.20 = 535 tonnes, or 35.7 per cent. (For the formulas, see break-even point and margin of safety.)

Step 4: payback at an assumed 70 per cent utilisation. Output = 70% × 1,500 = 1,050 tonnes. Contribution = 1,050 × 0.20 = 210.00. Less fixed charges 137.00 = profit before tax 73.00. Tax at an assumed 25 per cent = 18.25; profit after tax = 54.75. Annual cash accrual before interest = 54.75 + 30.00 depreciation + 17.00 interest = 101.75. Simple payback = 280.00 ÷ 101.75 = 2.75 years. Margin of safety = (1,050 − 685) ÷ 1,050 = 34.8 per cent.

Step 5: a cost overrun. If the plant cost rises 8 per cent (120.00 × 8% = 9.60), the contingency of 10.00 absorbs it with 0.40 to spare. If it rises 15 per cent (18.00), 8.00 remains to be funded: from extra promoter money, a larger loan, or a delay.

The answer: the unit costs ₹280.00 lakh, funded in full; it breaks even at 685 tonnes (45.7 per cent of capacity), pays back in 2.75 years at 70 per cent utilisation, and the contingency covers an 8 per cent rise in plant cost but not a 15 per cent one. The promoter decides whether to keep 8.00 lakh of reserve funding ready before work starts.

Simple payback ignores the time value of money and the years after payback; for net present value and the internal rate of return, see capital budgeting techniques.

Common mistakes

  1. Leaving out interest during construction, so the unit starts with an unfunded gap.
  2. A contingency set at zero because the quotations "look firm".
  3. Treating the margin money for working capital as the whole working capital need.
  4. Counting a subsidy as cash on day one when it arrives later.
  5. Preparing a feasibility study only for the bank, with the commercial part copied from a brochure instead of customer enquiries.
  6. Starting construction before the legal part (title, licences) is complete.

Where law touches the topic

Borrowing and security bring in company-law steps, covered in our posts on charges and the board's borrowing powers. This article is about the arithmetic of cost and funding.

Need help with your project's cost and funding statements?

If you are putting together a cost estimate and a funding plan for a new unit, our team can structure both statements, test the viability and prepare the papers for lenders. Start from our project funding page.

Key takeaways

  • Project cost is built head by head; interest during construction and a contingency belong in it.
  • Margin money for working capital is part of the cost; the whole working capital need is larger.
  • Means of finance must equal project cost exactly.
  • The feasibility study has technical, commercial, financial and legal parts; none can be skipped.
  • Break-even capacity and payback are first viability tests; test a cost overrun before it happens.

Read next

Disclaimer: The figures, rates, multiples and names in the worked example are invented for illustration and are not market data. Where the article refers to law, it is based on the Companies Act, 2013 (MCA consolidated text) and the rules and live guides linked, as consulted on 6 October 2026; valuation for income-tax and FEMA purposes follows its own rules. This article is general information, not valuation, lending or legal advice; check the official text before acting.

Quick recapKey facts & short answers

Key Facts About Project cost

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

What is the difference between project cost and means of finance?

Project cost is the total spend needed to build and start the unit. Means of finance is the list of sources that pays for it. They must tally.

Why is a contingency included?

Estimates change between quotation and delivery. A contingency keeps a small rise in prices from leaving the project short of funds.

Compliance is cheapest on the day it falls due and gets more expensive every day after.

— TaxClue Compliance Desk

Project cost: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related Services & Guides

Was this article helpful?
About the author
13,350 articles
Vikas Sharma Verified expert Tax & Compliance Expert

Experienced in company registration, GST, trademark, and compliance. Helping Indian businesses stay compliant.

Last reviewed: Live

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case — always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 7 questions readers ask most on this topic.

Project cost is the total spend needed to build and start the unit. Means of finance is the list of sources that pays for it. They must tally.

Estimates change between quotation and delivery. A contingency keeps a small rise in prices from leaving the project short of funds.

They overlap. A feasibility study decides whether the project should go ahead; a project report presents the chosen project, with its cost, funding and projections, to lenders and investors.

Lenders usually have a view on promoter contribution, and it varies by lender and project. Ask what applies to you; the figures in this article's example are assumptions.

Usually by the contingency first, then by extra promoter funds, a supplementary loan or a revised plan. Agree the order with your lender before construction.

It may, if confirmed and if the timing works. Because it often arrives later, a bridging arrangement may be needed.

No. It ignores timing of cash and what happens after payback. Use it with break-even and a discounted measure.