15 OCTPF & ESI · Contributions · Sep 2026in 3 days 20 OCTGSTR-3B · Summary return · Sep 2026in 8 days 21 OCTTax Audit Report · Form 3CA/3CB · AY 2026-27 · extended from 30 Sepin 9 days 30 OCTAOC-4 · Financial statements · FY 2025-26in 18 days 7 NOVTDS / TCS deposit · Deducted in Oct 2026in 26 days 11 NOVGSTR-1 · Outward supplies · Oct 2026in 30 days 21 NOVITR filing · Audit cases · AY 2026-27 · extended from 31 Octin 40 days 29 NOVMGT-7 / 7A · Annual return · FY 2025-26in 48 days
All due dates

Job costing: the job cost sheet, collecting material, labour and overhead for each order and quoting a price, with a worked example for a printing press

A job cost sheet collects, for one order, the direct material, direct labour and direct expenses actually used, adds overhead at the predetermined rate, and arrives at the total...

Published
Updated
Reading time
6 min
Views
29
Questions
6 answered
  • Expert Reviewed
  • Medium Complexity
Topic
Accounting Standards & Bookkeeping
Published
October 4, 2026
Last updated
Oct 12, 2026
Reading time
6 min
0:00
Last updated: October 2026Verified against: Government sources

A printing press, a fabrication shop or a repair garage does something different for each customer. The only way to know whether an order made money is to follow its cost from the first sheet of paper to delivery. Job costing does that, using a job cost sheet, and gives the owner both a way to quote and a way to check the quote afterwards.

When job costing fits and the data needed

Job costing suits work done to a customer's specification, where each order differs: printing, tool-making, contract fabrication, repairs, interiors. You need a job number on every material requisition and every labour ticket, department overhead rates (see the machine hour rate guide), a record of outside services bought for the job, and a way to track spoiled work. Firms that want job-wise profitability as a routine report can set it up with a costing and pricing analysis. For lots of identical items made for stock, see batch costing instead.

The method

  1. Estimate at quotation: material, labour hours, direct expenses, overhead, loading, profit.
  2. Open the job card with a job number on acceptance.
  3. Collect direct costs: material issued (less returns), labour tickets × rates, outside processing.
  4. Absorb overhead: department rate × hours (labour or machine) used by the job.
  5. Total and compare with the estimate on completion; record the reasons for differences.
  6. Spoiled and defective work. Normal spoilage inherent in the process is included in the job's cost (the estimate allows for it). Spoilage caused by a specific fault, such as a press error or a supplier's bad lot, is abnormal and is charged to the costing profit and loss account or recovered from the party at fault; rework for a defect normal to the job is charged to the job, while rework from an avoidable error is not.

Worked example: a printing press

The press prints 2,000 brochures for a customer (Job 101). All figures assumed.

Actual job cost

Cost headBasis₹
Art paperIssued, including a reprint after a colour mismatch100,000
Ink and platesIssued12,000
Direct labourComposing 15 h × 200 = 3,000; press 20 h × 250 = 5,000; binding 10 h × 150 = 1,5009,500
Direct expenseOutside lamination6,000
OverheadComposing 15 h × 100 = 1,500; press 20 machine h × 400 = 8,000; binding 10 h × 100 = 1,00010,500
Works cost138,000
Administration and selling load10 per cent of works cost13,800
Total job cost151,800

Check: 100,000 + 12,000 + 9,500 + 6,000 + 10,500 = 138,000. 10 per cent of 138,000 = 13,800. 138,000 + 13,800 = 151,800.

The quotation was built from the estimate below. Profit was loaded at 20 per cent on cost (assumed).

HeadEstimate (₹)Actual (₹)Variance (₹)
Paper92,000100,0008,000 over
Ink and plates12,00012,000nil
Direct labour10,0009,500500 under
Direct expense6,0006,000nil
Overhead11,00010,500500 under
Works cost131,000138,0007,000 over
Admin and selling load (10 per cent)13,10013,800700 over
Total cost144,100151,8007,700 over

Check: 92,000 + 12,000 + 10,000 + 6,000 + 11,000 = 131,000; 10 per cent = 13,100; total 144,100. Variance: 8,000 − 500 − 500 = 7,000 on works cost; 13,800 − 13,100 = 700; total 7,700.

Price quoted = 144,100 × 1.20 = ₹172,920 (profit planned 28,820). Actual profit = 172,920 − 151,800 = ₹21,120, which is ₹7,700 less than planned (28,820 − 21,120 = 7,700).

What the owner decides. The whole of the overrun is traceable: ₹8,000 of paper went into a reprint after a colour mismatch. That is avoidable spoilage, not a feature of the job. The owner should decide whether to record the reprint as abnormal and write it off to the costing profit and loss account, so job profit is not distorted, and whether the cause (a press setting or a proof approval step) needs a fix. The job's other lines were within ₹500 of the estimate, so the estimating method is sound. Had the quote been given at a fixed price with no room, the press would still have made ₹21,120, but the margin fell from about 16.7 per cent of price to about 12.2 per cent (21,120 ÷ 172,920).

How to read the result

Look at the total, but also at which line varied: material variances point to wastage, spoilage or price, labour variances to hours estimated or ticketed, overhead variances to the rate or the machine time. If the same line is wrong on many jobs, fix the estimating method, not the job. Where many jobs are costed, a standard costing view of material and labour variances helps.

Common mistakes

  • Not writing job numbers on requisitions and tickets, so costs fall into overhead.
  • Using one overhead rate for all departments.
  • Charging all spoilage to the job, which makes good jobs look poor.
  • Forgetting the administration and selling load when quoting.
  • Never comparing estimate with actual.
  • Charging a rework to the next customer's job.

Compare the layout with the period cost sheet: the heads are the same, but a job cost sheet is built per order rather than per month.

Need help with costing your orders?

If your quotes depend on memory, we can help set up job cards, department rates and an estimate-against-actual report as part of a costing and pricing analysis.

Key takeaways

  • A job cost sheet follows one customer's order with direct costs and absorbed overhead.
  • Quote from an estimate in the same layout as the actual so that the two compare line by line.
  • Normal spoilage is part of the job; abnormal spoilage is written off.
  • Always compare estimate and actual, and investigate the line that moved.
  • Job costing is for specific orders; batch costing is for lots of identical items.

Read next

Disclaimer: The methods described are standard cost accounting and financial management techniques. The worked example uses an invented business and invented figures, including any tax, interest or exchange rate, which are assumptions for illustration and not current rates. Where the article refers to a legal requirement, the linked guide and the official text should be checked. This article is general information, not legal advice; check the official text before acting.

Quick recapKey facts & short answers

Key Facts About Job costing

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

What is a job cost sheet?

It is a document, on paper or in software, that collects the material, labour, expenses and overhead of one customer order, from issue to completion.

How do I cost a job that spans two months?

Keep the job open and collect costs until completion. Incomplete jobs at month end are work-in-progress valued at cost to date.

One person should own every deadline. A deadline that belongs to everyone belongs to no one.

— TaxClue Compliance Desk

Job costing: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related Services & Guides

Was this article helpful?
About the author
13,350 articles
Vikas Sharma Verified expert Tax & Compliance Expert

Experienced in company registration, GST, trademark, and compliance. Helping Indian businesses stay compliant.

Last reviewed: Live

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case — always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 6 questions readers ask most on this topic.

It is a document, on paper or in software, that collects the material, labour, expenses and overhead of one customer order, from issue to completion.

Keep the job open and collect costs until completion. Incomplete jobs at month end are work-in-progress valued at cost to date.

At the predetermined rate for each department multiplied by the hours (machine or labour) the job used.

It is a pricing decision based on market, capacity and risk. State whether it is on cost or on selling price.

Record the rework or loss against the job if the customer's specification caused it, or to the costing profit and loss account if the press was at fault.

Yes. Consultants, repair shops and agencies use time sheets in place of material issues.