Capital work in progress — overdue and cost-overrun projects

Published
Updated
  • Medium Complexity
0:00
Last updated: September 2026Verified against: Government sources

The two CWIP disclosures

DisclosureWhat it shows
Ageing scheduleAmount in capital work in progress for less than 1 year, 1–2 years, 2–3 years and more than 3 years, split between projects in progress and projects temporarily suspended
Overdue and cost-overrunProject-wise details of projects whose completion is overdue or which have exceeded their cost compared to the original plan, with the period over which completion is expected

The ageing total shall tally with the amount of capital work in progress in the balance sheet.

Why capital work in progress attracts this treatment

CWIP is the balance sheet's most patient line

Capital work in progress is carried at cost and is not depreciated. A project that has stalled can therefore sit at full carrying value indefinitely, without the passage of time producing any charge in the accounts.

The two disclosures address that from opposite directions. The ageing schedule shows how long amounts have been sitting there. The overdue and cost-overrun disclosure shows which specific projects are not going to plan, and when the company expects them to finish.

Together they make it difficult for a stalled project to remain invisible.

The two-part structure of the overdue disclosure

It captures two different problems:

  1. Completion overdue: the project is late against its original schedule.
  2. Cost exceeded compared to the original plan: the project is over budget.

A project can be either, or both. Each is disclosed project-wise, so the reader sees which specific projects are affected rather than an aggregate.

And for each, the company must state the period over which completion is expected: a forward-looking statement about a project that has already missed its date.

"Projects temporarily suspended" is a judgement that is visible

The ageing schedule requires capital work in progress to be split between projects in progress and projects temporarily suspended.

Classifying a stalled project as in progress rather than temporarily suspended is a disclosure choice, and both an auditor and a reader can test it against the facts, whether expenditure is still being incurred, whether contractors remain engaged, whether the project has a live schedule. The category exists precisely to surface projects that have stopped.

Intangible assets under development

The same structure applies. The ageing runs in the same four buckets, split between projects in progress and projects temporarily suspended, and the total shall tally with the amount of intangible assets under development in the balance sheet. A further disclosure is required for those whose completion is overdue.

What the systems need to support this

  • A project register with, for each project: original planned completion date, original planned cost, current status, and expected completion date.
  • A status field distinguishing in progress from temporarily suspended, updated during the year rather than at year end.
  • Cost tracking against the original plan, not against a revised budget, the disclosure compares to the original plan.
  • Reconciliation of the project register to the capital work in progress general ledger balance.

The third point is the one most often got wrong. A project whose budget has been revised upward twice is not on plan simply because it is within the latest budget.

Compliance checklist

  • Age capital work in progress in the four buckets.
  • Split in progress from temporarily suspended, and classify honestly.
  • Tally the schedule to the balance sheet.
  • Disclose overdue and cost-overrun projects individually.
  • Compare cost to the original plan, not a revised budget.
  • State the expected completion period for each affected project.
  • Apply the same treatment to intangible assets under development.

Common mistakes

  • Classifying stalled projects as in progress.
  • Measuring overrun against a revised budget.
  • Aggregating overdue projects instead of listing them.
  • A schedule that does not tally to the balance sheet.
Quick recapKey facts & short answers

Key facts about capital work

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

What is the additional CWIP disclosure?

For capital work in progress whose completion is overdue, or which has exceeded its cost compared to the original plan, details are given project-wise with the period over which completion is expected.

How is CWIP aged?

In four buckets: less than 1 year, 1 to 2 years, 2 to 3 years and more than 3 years, with amounts shown separately for projects in progress and projects temporarily suspended.

An audit goes quickly when the schedules are ready before the auditor asks.

— TaxClue Accounts & Audit Desk

Capital Work: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related services & guides

Was this article helpful?
PC
About the author
Pawan Chaudhary Financial Advisor at TaxClue
Updated: Reviewed by Vikas Sharma

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case, always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 6 questions readers ask most on this topic.

For capital work in progress whose completion is overdue, or which has exceeded its cost compared to the original plan, details are given project-wise with the period over which completion is expected.

In four buckets: less than 1 year, 1 to 2 years, 2 to 3 years and more than 3 years, with amounts shown separately for projects in progress and projects temporarily suspended.

Yes. The total shall tally with the amount of capital work in progress in the balance sheet.

Yes: the same ageing structure and the same overdue and cost-overrun disclosure.

It is a separate line in the ageing schedule, which surfaces projects that have stopped rather than allowing them to sit within work in progress.

The period over which completion is expected.