Beyond the ageing schedule, Schedule III requires a separate disclosure for capital work in progress whose completion is overdue, or which has exceeded its cost compared to the original plan. Details are given project-wise, with the period over which completion is expected. The same applies to intangible assets under development.
The two CWIP disclosures
| Disclosure | What it shows |
|---|---|
| Ageing schedule | Amount in capital work in progress for less than 1 year, 1–2 years, 2–3 years and more than 3 years, split between projects in progress and projects temporarily suspended |
| Overdue and cost-overrun | Project-wise details of projects whose completion is overdue or which have exceeded their cost compared to the original plan, with the period over which completion is expected |
The ageing total shall tally with the amount of capital work in progress in the balance sheet.
Why capital work in progress attracts this treatment
Capital work in progress is carried at cost and is not depreciated. A project that has stalled can therefore sit at full carrying value indefinitely, without the passage of time producing any charge in the accounts.
The two disclosures address that from opposite directions. The ageing schedule shows how long amounts have been sitting there. The overdue and cost-overrun disclosure shows which specific projects are not going to plan, and when the company expects them to finish.
Together they make it difficult for a stalled project to remain invisible.
The two-part structure of the overdue disclosure
It captures two different problems:
- Completion overdue: the project is late against its original schedule.
- Cost exceeded compared to the original plan: the project is over budget.
A project can be either, or both. Each is disclosed project-wise, so the reader sees which specific projects are affected rather than an aggregate.
And for each, the company must state the period over which completion is expected: a forward-looking statement about a project that has already missed its date.
"Projects temporarily suspended" is a judgement that is visible
The ageing schedule requires capital work in progress to be split between projects in progress and projects temporarily suspended.
Classifying a stalled project as in progress rather than temporarily suspended is a disclosure choice, and both an auditor and a reader can test it against the facts, whether expenditure is still being incurred, whether contractors remain engaged, whether the project has a live schedule. The category exists precisely to surface projects that have stopped.
Intangible assets under development
The same structure applies. The ageing runs in the same four buckets, split between projects in progress and projects temporarily suspended, and the total shall tally with the amount of intangible assets under development in the balance sheet. A further disclosure is required for those whose completion is overdue.
What the systems need to support this
- A project register with, for each project: original planned completion date, original planned cost, current status, and expected completion date.
- A status field distinguishing in progress from temporarily suspended, updated during the year rather than at year end.
- Cost tracking against the original plan, not against a revised budget, the disclosure compares to the original plan.
- Reconciliation of the project register to the capital work in progress general ledger balance.
The third point is the one most often got wrong. A project whose budget has been revised upward twice is not on plan simply because it is within the latest budget.
Compliance checklist
- Age capital work in progress in the four buckets.
- Split in progress from temporarily suspended, and classify honestly.
- Tally the schedule to the balance sheet.
- Disclose overdue and cost-overrun projects individually.
- Compare cost to the original plan, not a revised budget.
- State the expected completion period for each affected project.
- Apply the same treatment to intangible assets under development.
Common mistakes
- Classifying stalled projects as in progress.
- Measuring overrun against a revised budget.
- Aggregating overdue projects instead of listing them.
- A schedule that does not tally to the balance sheet.