CWIP Ageing explained: this guide covers what it means, who it applies to, the step-by-step process, documents required, fees, due dates and penalties in India, so you can stay compliant with confidence and avoid costly mistakes.
The schedule ages expenditure, not projects. That single design choice explains almost every question the table raises.
The schedule
| CWIP | < 1 year | 1–2 years | 2–3 years | > 3 years | Total* |
|---|---|---|---|---|---|
| Projects in progress | |||||
| Projects temporarily suspended |
* Total shall tally with the CWIP amount in the balance sheet.
The disclosure is not required to be presented at asset or project level, however the total amount presented in this disclosure should tally with the total amount of CWIP as presented in the financial statements.
Ageing runs from initial recognition
As this disclosure needs to be provided at every balance sheet date, the ageing for an item of CWIP shall be determined from the date of its initial recognition to the date of the balance sheet.
Accordingly, it may so happen that for a single asset or project recognised as CWIP, the ageing for the total amount of CWIP shall fall into different ageing buckets as at a particular balance sheet date.
Company A is commissioning a plant, in progress at the end of year 4, with expenditure assumed incurred on the first day of each year:
Year 1: 100 (balance 100) · Year 2: 150 (balance 250) · Year 3: 250 (balance 500) · Year 4: 50 (balance 550)
The CWIP ageing disclosure at the end of year 4 spreads one project across all four buckets:
< 1 year: 50 · 1–2 years: 250 · 2–3 years: 150 · > 3 years: 100 · Total: 550
Each year's expenditure ages independently from the day it was recognised. A reader can therefore see how much of a balance is recent spend and how much has been sitting uncapitalised for years, which is the whole diagnostic value of the table.
Suspension that is part of the process
When temporary suspension is a necessary part of the process of getting an asset ready for its intended use, the project should not be considered to have been temporarily suspended and the CWIP related to such projects should continue to be presented under "Projects in progress".
A monsoon shutdown on a construction site, or a mandated curing period, is not a suspended project.
Classification is a point-in-time test
The classification of assets and projects into "projects in progress" and "projects temporarily suspended" needs to be evaluated at each reporting date. Any change in status during the reporting period or any time after the end of the reporting period will not change the classification for disclosure purposes.
- Suspended for most of the year but development resumes before the year end → presented under projects in progress.
- Suspended at the year end but development resumes after the year end → presented under projects temporarily suspended.
And comparatives are not restated: where a project is in progress at the end of the current period but was temporarily suspended at the end of the previous period, the current schedule shows it under "projects in progress" while the previous period's schedule continues to present it under "projects temporarily suspended".
Two extensions
The CWIP ageing requirements shall be applicable for investment property under development. And for intangible assets under development, an identical ageing schedule applies, with all the relevant guidance given for CWIP applicable to the extent relevant.
Common mistakes
- Ageing the whole project balance from the date the project began.
- Classifying a necessary process pause as a temporarily suspended project.
- Restating the comparative schedule when a project's status changes.
- Omitting investment property under development from the schedule.