30 OCTAOC-4 · Financial statements · FY 2025-26tomorrow 7 NOVTDS / TCS deposit · Deducted in Oct 2026in 9 days 11 NOVGSTR-1 · Outward supplies · Oct 2026in 13 days 15 NOVPF & ESI · Contributions · Oct 2026in 17 days 20 NOVGSTR-3B · Summary return · Oct 2026in 22 days 21 NOVITR filing · Audit cases · AY 2026-27 · extended from 31 Octin 23 days 29 NOVMGT-7 / 7A · Annual return · FY 2025-26in 31 days 15 DECAdvance Tax · 3rd (75%) instalment · FY 2026-27in 47 days
All due dates

Completion Schedule Under Schedule III: Overdue Projects and Overruns

Required only where actual cost has already exceeded the original estimate or actual timelines have already exceeded the original plan — and measured against the original plan...

Published
Updated
Reading time
4 min
Questions
6 answered
  • Medium Complexity
Topic
Accounting Standards & Bookkeeping
Published
September 7, 2026
Last updated
Sep 7, 2026
Reading time
4 min
0:00
Last updated: September 2026Verified against: Government sources

What triggers it

For capital work-in-progress whose completion is overdue or has exceeded its cost compared to its original plan, a completion schedule shall be given:

CWIP< 1 year1–2 years2–3 years> 3 years
Projects in progress — Project 1, Project 2 …
Projects temporarily suspended — Project 1, Project 2 …

Details of projects where activity has been suspended shall be given separately. Unlike the ageing schedule, this one is made at project level, and separately for the two categories.

Already exceeded, not expected to exceed

Disclosure is required only in those cases where the actual cost of an asset or project has already exceeded the estimated cost as per the original plan, or actual timelines for completion have already exceeded the estimated timelines as per the original plan. Such assessment needs to be done at each reporting date.

An anticipated overrun does not trigger the completion schedule; a realised one does. The schedule then discloses expected completion timelines in defined ageing brackets — so the columns look forward even though the trigger looks back.

Original plan versus revised plan

Any variation between a project's actual completion timeline or actual cost and the respective estimate is required to be evaluated from the original plan — original completion timelines and original estimated costs.

The original plan is that plan which is approved by the relevant approving authority and on the basis of which implementation progress is evaluated. It includes management's estimates and assumptions with respect to future business, economy / industry and regulatory environments, and those assumptions shall be subject to change from time to time, resulting in a "revised plan".

The rule that gives the disclosure its force: when plans are subsequently revisited and revised, the same should not be considered for determining variation when making the above disclosures.

Without it, a delayed project could be re-baselined each year and would never be overdue against its own most recent plan. Management shall apply judgement in determining whether such revisions in the plans are in the nature of a fresh "original plan" or simply an update of estimates and assumptions — a judgement that has to be exercised honestly, because it is the only route by which a new baseline can legitimately be adopted.

What is a project

Neither Schedule III nor Ind AS 16 defines "project". It may be construed as the smallest group of assets having a common intended use — for example, a group of assets in an integrated plant may be treated as one project.

The identification of a project will require judgement, and management needs to identify projects based on the facts of each case. Project identification should be consistent with how management identifies and monitors progress on a group of assets internally.

Two presentation reliefs

  1. Aggregation. Projects that are not considered material at an individual level can be aggregated and disclosed under the relevant category.
  2. Combined or separate triggers. The prescribed format seems to require a disclosure for both categories — exceeded cost or overdue — on a combined basis instead of separately disclosing for projects which are overdue and projects where costs have exceeded. However, the company may choose to provide disclosure for each trigger separately.

Intangible assets under development

An identical completion schedule applies to intangible assets under development whose completion is overdue or has exceeded its cost compared to its original plan, with details of projects where activity has been suspended given separately and all the relevant CWIP guidance applicable to the extent it applies.

Common mistakes

  • Measuring variation against the latest revised plan.
  • Disclosing projects merely expected to overrun.
  • Presenting the completion schedule at aggregate rather than project level.
  • Combining suspended projects with those in progress.
Quick recapKey facts & short answers

Key Facts About Completion Schedule

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

When is a completion schedule required?

For capital work-in-progress whose completion is overdue or has exceeded its cost compared to its original plan, and correspondingly for intangible assets under development.

What does the schedule show?

Expected completion timelines in defined ageing brackets — to be completed in less than 1 year, 1-2 years, 2-3 years, more than 3 years — project by project, with details of projects where activity has been suspended given separately.

One person should own every deadline. A deadline that belongs to everyone belongs to no one.

— TaxClue Compliance Desk

Completion Schedule: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related Services & Guides

Was this article helpful?
About the author
Vikas Sharma Tax & Compliance Expert at TaxClue

Experienced in company registration, GST, trademark, and compliance. Helping Indian businesses stay compliant.

Updated:

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case — always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 6 questions readers ask most on this topic.

For capital work-in-progress whose completion is overdue or has exceeded its cost compared to its original plan, and correspondingly for intangible assets under development.

Expected completion timelines in defined ageing brackets — to be completed in less than 1 year, 1-2 years, 2-3 years, more than 3 years — project by project, with details of projects where activity has been suspended given separately.

The plan approved by the relevant approving authority and on the basis of which implementation progress is evaluated. It includes management estimates and assumptions about future business, economy, industry and regulatory environments, which may change from time to time resulting in a revised plan.

No. When plans are subsequently revisited and revised, the same should not be considered for determining variation when making these disclosures. Management shall apply judgement in determining whether a revision is in the nature of a fresh original plan or simply an update of estimates and assumptions.

No. Disclosure is required only where the actual cost of an asset or project has already exceeded the estimated cost as per the original plan, or actual timelines have already exceeded the estimated timelines. Such assessment needs to be done at each reporting date.

Yes. Projects that are not considered material at an individual level can be aggregated and disclosed under the relevant category.