Predecessor Practitioner explained: this guide covers what it means, who it applies to, the step-by-step process, documents required, fees, due dates and penalties in India — so you can stay compliant with confidence and avoid costly mistakes.
Paragraph R5320.4 requires a sustainability assurance provider to determine whether there are any reasons for not accepting an engagement when asked to replace another practitioner, when tendering against one, or when taking on work complementary or additional to another practitioner's. Paragraphs R5320.6 to R5320.8 set out the communications that follow.
The three triggers
Paragraph R5320.4 applies when the practitioner:
- (a) Is asked by a potential client to replace another sustainability assurance provider;
- (b) Considers tendering for an engagement held by a different practitioner for a sustainability assurance client; or
- (c) Considers undertaking work for a client that is complementary or additional to that of a different practitioner.
Limb (c) is the one most often missed. Adding a workstream alongside an incumbent — a second assurance scope, a different metric, a different reporting framework — engages the same requirement as displacing the incumbent altogether.
The threat: incomplete information
Paragraph 5320.4 A1 explains that there might be reasons for not accepting an engagement, one being that a threat cannot be addressed by applying safeguards. It gives the example of a self-interest threat to professional competence and due care if the practitioner accepts the engagement before knowing all the relevant facts.
Paragraph 5320.4 A2 applies the same reasoning to limb (c): where the practitioner is asked to undertake work complementary or additional to that of an existing or predecessor practitioner, a self-interest threat to professional competence and due care might be created as a result of incomplete information.
Paragraph 5320.4 A3 names, as a factor in evaluating the threat, whether tenders state that, before accepting the engagement, contact with the existing or predecessor practitioner will be requested. The Code explains why: that contact "gives the proposed practitioner the opportunity to inquire whether there are any reasons why the engagement should not be accepted." A firm that writes this into its tender responses as standard improves its own threat position before the question arises.
The safeguards
Paragraph 5320.4 A4 gives two:
- Asking the existing or predecessor practitioner to provide any known information of which, in that practitioner's opinion, the proposed practitioner needs to be aware before deciding whether to accept. The Code notes such inquiry might reveal previously undisclosed pertinent facts and might indicate disagreements with the existing or predecessor practitioner that might influence the decision.
- Obtaining information from other sources — inquiries of third parties, or background investigations regarding senior management or those charged with governance of the client.
Making contact: permission first
Paragraph 5320.5 A1 states that a proposed practitioner will usually need the client's permission, preferably in writing, to initiate discussions with the existing or predecessor practitioner. That permission is the client's to give, and its absence is not a technicality — it is information in itself.
Paragraph R5320.6 covers the case where contact cannot be made at all: the proposed practitioner shall take other reasonable steps to obtain information about any possible threats. Inability to speak to the incumbent does not end the inquiry; it redirects it.
Replying: the existing practitioner's duty
Paragraph R5320.7 requires the existing or predecessor practitioner asked to respond to:
- (a) Comply with relevant laws and regulations governing the request; and
- (b) Provide any information honestly and unambiguously.
Paragraph 5320.7 A1 sets the limit: the existing or predecessor practitioner is bound by confidentiality, and whether discussion is permitted depends on the nature of the engagement and on (a) whether the client has given permission, and (b) the legal and ethics requirements relating to such communications and disclosure. Paragraph 5320.7 A2 points to paragraph 5114.3 A1 for the circumstances in which disclosure of confidential information is required or appropriate.
"Honestly and unambiguously" is the operative standard. A reply that is literally accurate but constructed to avoid conveying a known problem does not satisfy R5320.7(b).
The stricter rule for engagements within the Independence Standards
Paragraph R5320.8 raises the obligation where the engagement is within the scope of the Independence Standards in this Part. There, the proposed practitioner shall request the existing or predecessor practitioner to provide known information regarding any facts or other information of which, in that practitioner's opinion, the proposed practitioner needs to be aware before deciding whether to accept. Then:
- (a) If the client consents to disclosure, the existing or predecessor practitioner shall provide the information honestly and unambiguously; and
- (b) If the client fails or refuses to grant permission to discuss its affairs, the existing or predecessor practitioner shall disclose this fact to the proposed practitioner, who shall carefully consider such failure or refusal when determining whether to accept the appointment.
The client's refusal to permit the conversation does not merely leave the proposed practitioner uninformed. Under R5320.8(b) the refusal itself must be disclosed by the existing or predecessor practitioner and must be carefully considered by the proposed practitioner in the acceptance decision. A client that will not allow the incumbent to speak has told the proposed practitioner something material, and the Code requires that to be weighed rather than set aside.
Practical checklist
- Apply R5320.4 on all three triggers, including work merely complementary or additional to an incumbent's.
- State in tender responses that contact with the existing or predecessor practitioner will be requested before acceptance.
- Obtain the client's permission for that contact in writing.
- Where contact is impossible, record the other reasonable steps taken under R5320.6.
- When replying as the incumbent, check the client's permission and the legal position, then answer honestly and unambiguously.
- For an engagement within the Independence Standards, make the request required by R5320.8 and record how a refusal was considered.
- Do not accept before knowing the relevant facts — that is the named self-interest threat.
Common mistakes
- Applying the section only when replacing an incumbent, not when supplementing one.
- Contacting the incumbent without the client's permission.
- Treating an unreachable incumbent as the end of the inquiry instead of triggering R5320.6.
- Replying to a successor with a technically true but evasive answer.
- Treating a refusal of permission as neutral when R5320.8(b) requires it to be carefully considered.
- Accepting first and gathering facts afterwards.