Paragraph 4.28 of the Policy sets the time limit for exports under a DFIA (the Policy's abbreviation for the duty-exempt import authorisation scheme), the separate authorisation for each norm, and the validity of the transferable authorisation, which is 12 months with no revalidation. Paragraph 4.29 lists inputs that need a declaration of technical characteristics. Paragraphs 4.54 to 4.56 of the Handbook add the split of an authorisation, re-export of defective goods and accounts.
This article is based on the chapter-wise text of the Foreign Trade Policy, 2023 published on the DGFT website, as consulted on 2 October 2026; the copy carries no "updated up to" date. The procedure is taken from Chapter 4 of the Handbook of Procedures, 2023 as published on the DGFT website (file of July 2026), consulted on 2 October 2026. Later Notifications and Public Notices should be checked. A holder planning to sell or split a transferable authorisation can first take advice through a legal consultation.
The applicant files online before starting export, and the export must be completed within 12 months of online filing and generation of the file number (paragraph 4.28(i), (ii)). A separate DFIA is issued for each SION (4.28(vi)). The Regional Authority issues a transferable DFIA valid for 12 months from issue, with no revalidation (4.28(viii)). Paragraph 4.29 requires a declaration in the shipping bill for listed sensitive inputs. Handbook paragraph 4.54 allows split authorisations of at least Rs. 10 lakh CIF each.
What the Policy says
Paragraph 4.28: validity and transferability
| Sub-paragraph | Rule |
|---|---|
| (i) | The applicant files the online application to the Regional Authority concerned before starting export under the DFIA. |
| (ii) | Export must be completed within 12 months from the date of online filing of the application and generation of the file number. |
| (iii) | While exporting or supplying, the applicant indicates the file number on the export or supply documents: shipping bill, bill of export or tax invoice for supply under the GST rules. |
| (iv) | Following paragraph 4.12 of the Policy, where a SION permits a generic or alternative input, the specific input and quantity used must be endorsed in the shipping bill, bill of export or tax invoice; only those inputs, in proportion to the quantity actually used within the overall quantity, are permitted for import in the authorisation. |
| (v) | Where a SION gives a single quantity against more than one input, quantities permitted are in proportion to what was used and declared, within the overall group quantity; the proportion must be shown clearly in the export document. |
| (vi) | A separate DFIA is issued for each SION. |
| (vii) | Exports are made from any port listed in paragraph 4.35 of the Handbook; a separate application is made for EDI and non-EDI ports, and for each non-EDI port. |
| (viii) | The Regional Authority issues a transferable DFIA with validity of 12 months from the date of issue. No further revalidation is granted. |
Two points from the table need care. First, the 12 months in (ii) and the 12 months in (viii) are different clocks. The first runs from online filing and the file number and limits exports; the second runs from the date of issue of the DFIA and limits its use. Second, (iv) and (v) repeat the idea of paragraph 4.12 for the DFIA: see our article on paragraphs 4.12 to 4.15. For the ports of paragraph 4.35 of the Handbook, see the article on paragraphs 4.34 and 4.35 of the Handbook.
Paragraph 4.29: sensitive inputs
Under 4.29(a), for the inputs the paragraph lists, the exporter must give a declaration of technical characteristics, quality and specification in the shipping bill. The list is a series of material names (alloy steel, copper alloy, synthetic rubber, bearings and others); this article does not retype it, and the paragraph should be consulted for the exact entries. Under 4.29(b), while issuing the DFIA the Regional Authority must mention the technical characteristics, quality and specification of those inputs in the authorisation. The paragraph is a documentation rule: it does not prohibit any input.
What the Handbook requires
- Paragraph 4.54: split DFIA. Split authorisations, each with a CIF value of at least Rs. 10 lakh and multiples of it, may be issued on request at the time of seeking transferability. Split DFIAs have the same port of registration as the original.
- Paragraph 4.55: re-export of goods imported under a DFIA. Goods imported against a transferable DFIA that are found defective or unfit for use may be re-exported, as per Department of Revenue guidelines. If the goods were not put to use after import, the concerned Commissioner of Customs generates a certificate to the extent of 95% of the CIF value debited against the DFIA, with the amount and description of exported goods and details of the original DFIA. On that certificate, the Regional Authority issues a fresh DFIA with the same port of registration, valid for the balance period available on the date of import of the defective goods.
- Paragraph 4.56: accounts. The original DFIA holder keeps a true and proper account of consumption and utilisation of goods imported or procured domestically without payment of duty, against each authorisation, as prescribed in Appendix 4H. The records are filed online to the Regional Authority with the request for transferability. Appendix 4H is named only.
The application and eligibility are in our article on paragraphs 4.24 to 4.27. The Policy is made under section 5 of the Foreign Trade (Development and Regulation) Act, 1992 (section 5 of the FTDR Act); the Handbook is issued by the Director General under section 6 (section 6 of the FTDR Act). The Policy is not a statute; it binds through the Act and the conditions of each authorisation.
A worked example
Pillai Metals Private Limited, an invented exporter, files its DFIA application online and receives a file number. It must complete the exports within 12 months of that date (paragraph 4.28(ii)) and put the file number on every shipping bill (paragraph 4.28(iii)). It exports under two SIONs and so needs two DFIAs (paragraph 4.28(vi)). After realisation it asks for a transferable DFIA, which the Regional Authority issues with 12 months' validity from issue and no revalidation (paragraph 4.28(viii)). It then asks for a split into two authorisations, each of at least Rs. 10 lakh CIF, for sale to two buyers (paragraph 4.54); both keep the original port of registration. One buyer finds part of the imported goods defective and unused: after re-export the Commissioner of Customs certifies up to 95% of the CIF value debited, and a fresh DFIA is issued for the balance period (paragraph 4.55).
Need help with a transferable DFIA?
The two 12-month clocks, the split and the declarations for sensitive inputs each have their own consequences. Our team can check your timeline and documents in a legal consultation before you export or transfer.
Key takeaways
- File online before starting export; complete exports within 12 months of filing and the file number (paragraph 4.28(i) and (ii)).
- Put the file number on export documents (paragraph 4.28(iii)); a separate DFIA for each SION (paragraph 4.28(vi)).
- Transferable DFIA: 12 months from issue, no revalidation (paragraph 4.28(viii)).
- Sensitive inputs need a technical declaration in the shipping bill and a mention in the authorisation (paragraph 4.29).
- Split DFIA: at least Rs. 10 lakh CIF each (Handbook paragraph 4.54).
- Defective goods: re-export, certificate up to 95% of CIF value, fresh DFIA (Handbook paragraph 4.55).
Read next
- Paragraphs 4.24 to 4.27 of the Foreign Trade Policy, 2023: DFIA scheme eligibility and value addition
- Paragraphs 4.34 and 4.35 of the Handbook of Procedures, 2023: Bank Guarantee, Legal Undertaking and port of registration
- DFIA against Advance Authorisation: the IGST difference
- Duty exemption schemes under the Foreign Trade Policy
Disclaimer: Based on the chapter-wise text of the Foreign Trade Policy, 2023 and the Handbook of Procedures, 2023 published on the DGFT website, and on the later Notifications named in this article, as consulted on 2 October 2026. The copies carry no "updated up to" date. Notifications, Public Notices, Trade Notices, the ITC(HS) schedules, Appendices and forms change often; the current text on the DGFT website should be checked before acting. This article is general information, not legal advice; check the official text before acting.