Mergers and Acquisitions explained: this guide covers what it means, who it applies to, the step-by-step process, documents required, fees, due dates and penalties in India, so you can stay compliant with confidence and avoid costly mistakes.
Where a merger or acquisition brings a new entity inside a sustainability assurance client, paragraphs R5400.71 to R5400.76 govern what happens to the firm's existing interests and relationships with that entity, ending them by the effective date if possible, and continuing only on strict conditions with a six-month outer limit if not.
The trigger
Paragraph 5400.70 A1 describes the situation that mergers and acquisitions create:
"An entity might become a related entity of a sustainability assurance client because of a merger or acquisition. A threat to independence and, therefore, to the ability of a firm to continue a sustainability assurance engagement might be created by previous or current interests or relationships between a firm or network firm and such a related entity."
The problem is created by someone else's transaction. The firm has done nothing; a corporate event has pulled an entity it deals with inside the boundary of a client it assures. Mergers and acquisitions are therefore treated separately from ordinary independence breaches, with their own transitional machinery in paragraphs R5400.71 to R5400.76.
Step one: identify, evaluate, and end
Paragraph R5400.71 requires the firm to:
- (a) Identify and evaluate previous and current interests and relationships with the related entity that, taking into account any actions taken to address the threat, might affect its independence and therefore its ability to continue the engagement after the effective date; and
- (b) Subject to R5400.72, take steps to end any interests or relationships that are not permitted by the Code by the effective date of the merger or acquisition.
The default is clean: on mergers and acquisitions, impermissible interests go by the effective date.
Step two: when the interest cannot reasonably be ended
Paragraph R5400.72 is the exception to R5400.71(b). Where the interest or relationship cannot reasonably be ended by the effective date, the firm shall:
- (a) Evaluate the threat created by the interest or relationship; and
- (b) Discuss with those charged with governance the reasons why it cannot reasonably be ended by the effective date, and the evaluation of the level of the threat.
Paragraph 5400.72 A1 gives the typical reason: the firm provides a non-assurance service to the related entity, which the entity is not able to transition in an orderly manner to another provider by that date. Paragraph 5400.72 A2 gives the factors for evaluating the level of a threat created by mergers and acquisitions where interests and relationships cannot reasonably be ended:
- The nature and significance of the interest or relationship.
- The nature and significance of the related entity relationship: for example, whether the related entity is a subsidiary or parent.
- The length of time until the interest or relationship can reasonably be ended.
Step three: the conditions for continuing
Paragraph R5400.73 applies where, following that discussion, those charged with governance request the firm to continue. The firm shall do so only if:
| Condition | |
|---|---|
| (a) | The interest or relationship will be ended as soon as reasonably possible but no later than SIX MONTHS after the effective date of the merger or acquisition |
| (b) | Any individual who has such an interest or relationship — including one arising through performing a non-assurance service that would not be permitted by Section 5600 and its subsections — will not be a member of the engagement team for the engagement or the individual responsible for the engagement quality control review |
| (c) | Transitional measures will be applied, as necessary, and discussed with those charged with governance |
Condition (a) has two parts and they are not the same. The interest must be ended as soon as reasonably possible, and in any event no later than six months after the effective date. A firm that could have ended an interest in six weeks and took five months has not complied merely because it stayed inside the outer limit.
Condition (b) is also worth reading twice: it names the engagement quality control reviewer separately from the engagement team, because under paragraph 5400.12 the reviewer is a sustainability assurance team member but not an engagement team member. Excluding someone from the team alone would not exclude them from the review role.
Paragraph 5400.73 A1 gives examples of transitional measures:
- Having a sustainability assurance provider review the assurance or non-assurance work as appropriate.
- Having a sustainability assurance provider who is not a member of the firm expressing the opinion perform a review equivalent to an engagement quality control review.
- Engaging another firm to evaluate the results of the non-assurance service, or to re-perform it to the extent necessary to enable that other firm to take responsibility for the service.
The short-completion route
Paragraph R5400.74 covers a narrower case: the firm might have completed a significant amount of work before the effective date and be able to complete the remaining assurance procedures within a short period of time. If those charged with governance request the firm to complete the engagement while continuing with the interest or relationship, the firm shall only do so if it:
- (a) Has evaluated the level of the threat and discussed the results with those charged with governance;
- (b) Complies with R5400.73(b) to (c): the personnel exclusion and the transitional measures; and
- (c) Ceases to perform the engagement no later than the date the sustainability assurance report is issued.
This route buys completion of the current engagement, not continuation of the relationship through the mergers and acquisitions transition. Condition (c) ends it at the report.
The override: if objectivity remains compromised
R5400.75, "Even if all the requirements of paragraphs R5400.71 to R5400.74 could be met, the firm shall determine whether the circumstances identified in paragraph 5400.70 A1 create a threat that cannot be addressed such that objectivity would be compromised. If so, the firm shall cease to perform the sustainability assurance engagement."
This is a genuine override, and it is why the mergers and acquisitions provisions cannot be run as a compliance checklist. Satisfying every condition is a necessary but not sufficient basis for continuing; the firm must still form and record a judgment that objectivity is not compromised.
Mandatory documentation
Paragraph R5400.76 requires the firm to document:
- (a) Any interests or relationships identified in 5400.70 A1 that will not be ended by the effective date, and the reasons why;
- (b) The transitional measures applied;
- (c) The results of the discussion with those charged with governance; and
- (d) The reasons why the previous and current interests and relationships do not create a threat such that objectivity would be compromised.
Limb (d) is the written form of the R5400.75 override, and it is a requirement, not an encouragement.
Practical checklist
- Monitor client mergers and acquisitions; the trigger is a third party's transaction, not the firm's own act.
- On announcement of any of the mergers and acquisitions affecting a client, inventory all firm and network interests and relationships with the target or acquirer.
- Plan to end impermissible ones by the effective date as the default.
- Where that is not reasonably possible, evaluate and discuss with those charged with governance before the date.
- If continuing, fix an end date that is as soon as reasonably possible and inside six months.
- Exclude affected individuals from both the engagement team and the engagement quality control review role.
- Apply and discuss transitional measures, and record all four items required by R5400.76.
- Make and record the R5400.75 judgment separately from the conditions.
Common mistakes
- Treating six months as the permitted period after mergers and acquisitions, rather than an outer limit.
- Excluding an individual from the engagement team but leaving them as quality control reviewer.
- Continuing without a request from those charged with governance, which R5400.73 requires.
- Using the R5400.74 route to continue the relationship past the report date.
- Treating the conditions as sufficient and skipping the R5400.75 objectivity judgment.
- Omitting the R5400.76(d) reasoning from the file.