30 OCTAOC-4 · Financial statements · FY 2025-26tomorrow 7 NOVTDS / TCS deposit · Deducted in Oct 2026in 9 days 11 NOVGSTR-1 · Outward supplies · Oct 2026in 13 days 15 NOVPF & ESI · Contributions · Oct 2026in 17 days 20 NOVGSTR-3B · Summary return · Oct 2026in 22 days 21 NOVITR filing · Audit cases · AY 2026-27 · extended from 31 Octin 23 days 29 NOVMGT-7 / 7A · Annual return · FY 2025-26in 31 days 15 DECAdvance Tax · 3rd (75%) instalment · FY 2026-27in 47 days
All due dates
GST

HAM Road Contracts: Time of Supply Under Circular 221

A Hybrid Annuity Mode contract with NHAI is a single agreement covering construction of a highway and its operation and maintenance, sometimes for fifteen or twenty years. The...

Published
Updated
Reading time
6 min
Questions
6 answered
  • Medium Complexity
Topic
GST
Published
September 5, 2026
Last updated
Sep 5, 2026
Reading time
6 min
0:00
Last updated: September 2026Verified against: Government sources

A Hybrid Annuity Mode contract with NHAI is a single agreement covering construction of a highway and its operation and maintenance, sometimes for fifteen or twenty years. The concessionaire receives a portion of the cost during construction and the balance as annuities spread across the O&M period, with interest.

Two readings were possible, and they produced very different cash flows for the concessionaire.

Circular No. 221/15/2024-GST dated 26 July 2024 chose one.

The two readings

Reading one — fragmented. Construction is a discrete supply completed when the road is built. Tax on the entire construction value falls due then, even though most of the money will arrive over the following twenty years. The O&M is then a separate continuous supply.

Reading two — holistic. The contract is one composite arrangement, with staggered payment terms that hold the concessionaire accountable for both building and maintaining the highway. It is a continuous supply of services, and the tax point follows the payments.

The first reading creates a very large early liability against payments not yet received — a working-capital problem severe enough to affect project viability. The circular adopted the second.

What the circular says

The ICAI commentary records the reasoning: a HAM contract is a single contract for construction as well as operation and maintenance of the highway; the payment terms are so staggered that the concessionaire is held accountable for the repair and maintenance of the highway as well; and the contract needs to be looked at holistically based on the services to be performed by the concessionaire.

Read that way, the arrangement satisfies s.2(33) — a supply provided or agreed to be provided continuously or on a recurrent basis under a contract, for a period exceeding three months, with periodic payment obligations.

The consequence: section 31(5)

Once the arrangement is a continuous supply of services, s.31(5) applies.

Where the due date of payment is ascertainable from the contract — which it invariably is in a concession agreement with a defined annuity schedule — the invoice must be issued on or before that due date. The time of supply follows under s.13(2).

So:

  • during the construction period, tax follows the construction instalments as they fall due;
  • during the O&M period, tax follows the annuity instalments as they fall due;
  • no liability crystallises on the completion of construction as such.

Continuous supply of services and section 31(5) →

The interest component

Annuities under a HAM contract typically carry an interest or finance component reflecting the deferral.

Where interest is charged for delayed payment of consideration, s.15(2)(d) includes it in the value of the supply — at the rate applicable to that supply, not at a separate rate.

Where the interest is a contractually agreed component of the annuity itself, rather than a charge for delay, the analysis is that it forms part of the consideration for the continuous supply, and is taxed with it. Concession agreements should be read closely on this point, because the characterisation determines both the value and the rate.

Beyond HAM: the general principle

The circular is written for NHAI HAM projects, but the reasoning has wider reach. Wherever a single infrastructure or concession contract:

  • covers construction plus a long operating obligation;
  • is paid through staggered instalments or annuities; and
  • is structured so that payment is contingent on continued performance,

the holistic reading and the continuous supply analysis are available on the same logic.

That covers a range of PPP structures — annuity road projects outside HAM, some BOT variants, and long-term O&M-linked supply contracts in power and water.

It does not convert every long contract into a continuous supply. The definition still requires periodic payment obligations under the contract, and a contract paying a lump sum on completion with a separate maintenance agreement is two arrangements, not one.

Practical notes

  • Anchor the analysis in the concession agreement's payment schedule. It is the evidence for both the continuous supply characterisation and the s.31(5)(a) due dates.
  • Invoice on or before each due date, not on receipt. Late invoicing moves the tax point to the date of provision of service under s.13(2)(b) without improving the timing.
  • Non-receipt does not defer liability. An annuity that falls due and is not paid still creates a tax point.
  • Separate the interest component in the contract and in the invoice, and take a documented position on its treatment.
  • Reconcile to GSTR-9C. A long project with annuity-based tax points will show a permanent books-to-returns timing difference that must be explained.

Key takeaways

  • Circular No. 221/15/2024-GST directs a holistic reading of a HAM contract.
  • The arrangement is a continuous supply of services under s.2(33).
  • s.31(5)(a) applies — invoice on or before each payment due date.
  • No lump-sum liability arises on completion of construction.
  • The interest component of an annuity needs a documented characterisation.
  • The reasoning extends to other annuity-based concession structures on the same facts.

Read next

Disclaimer: Positions stated as on 5 September 2026, based on ICAI Background Material on GST, Volume I (2026 edition) and Circular No. 221/15/2024-GST.

Quick recapKey facts & short answers

Key Facts About HAM Road Contracts

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

How is GST charged on a HAM contract?

As a continuous supply of services. Circular No. 221/15/2024-GST directs that the contract be read holistically, so tax follows the instalment and annuity due dates rather than arising on completion of construction.

Is tax payable on the whole construction value when the road is complete?

No. The holistic reading treats the arrangement as one continuous supply with periodic payment obligations, so the tax point follows each payment due date.

Cancelling a registration does not cancel the returns that were already due.

— TaxClue GST Desk

HAM Road Contracts: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related Services & Guides

Was this article helpful?
About the author
Vikas Sharma Tax & Compliance Expert at TaxClue

Experienced in company registration, GST, trademark, and compliance. Helping Indian businesses stay compliant.

Updated:

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case — always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 6 questions readers ask most on this topic.

As a continuous supply of services. Circular No. 221/15/2024-GST directs that the contract be read holistically, so tax follows the instalment and annuity due dates rather than arising on completion of construction.

No. The holistic reading treats the arrangement as one continuous supply with periodic payment obligations, so the tax point follows each payment due date.

Section 31(5)(a), where the due date of payment is ascertainable from the contract — the invoice must be issued on or before that due date.

The liability still arises. The tax point is fixed by the due date, not by receipt.

Interest for delayed payment is included in value under section 15(2)(d) at the supply's own rate. A contractually agreed finance component within the annuity generally forms part of the consideration for the continuous supply.

It is written for NHAI HAM contracts, but the reasoning applies where a single contract covers construction plus a long operating obligation paid through staggered instalments contingent on performance.