Next due
30 OCTAOC-4 · Financial statements · FY 2025-26in 5 days 7 NOVTDS / TCS deposit · Deducted in Oct 2026in 13 days 11 NOVGSTR-1 · Outward supplies · Oct 2026in 17 days 15 NOVPF & ESI · Contributions · Oct 2026in 21 days 20 NOVGSTR-3B · Summary return · Oct 2026in 26 days 21 NOVITR filing · Audit cases · AY 2026-27 · extended from 31 Octin 27 days 29 NOVMGT-7 / 7A · Annual return · FY 2025-26in 35 days 15 DECAdvance Tax · 3rd (75%) instalment · FY 2026-27in 51 days
All due dates
Customs Live

Table to the Project Imports Regulations, 1986: the eligible plants and projects and their sponsoring authorities, with the 2023 solar exclusion and the 2025 Jaipur Metro entry

Each row of the Table pairs a plant or project with a sponsoring authority. The importer takes the approved list of items from that authority (regulation 5(4)). Serial 4, "Any...

Published
Updated
Reading time
9 min
Questions
6 answered
  • High Complexity
  • In-Depth Guide
Topic
Customs
Published
October 3, 2026
Last updated
Oct 3, 2026
Reading time
9 min
0:00
Last updated: October 2026Verified against: Government sources

The Table annexed to the Project Imports Regulations, 1986 lists the plants and projects that can use heading 98.01 and names, against each, the sponsoring authority whose clearance and approved list of items the importer needs. The Table has been changed twice since 2022: from 2 February 2023 solar power plants and projects are carved out of the "any other" entry, and from 29 November 2025 Jaipur Metro Projects were added to the metro rail entry.

Position of the text: as amended up to Notification No. 49/2025-Customs dated 28 November 2025. Later notifications should be checked; no official consolidated text exists. The entries below follow the serial numbers as printed. Addresses given against sponsoring authorities in the Table are left out here.

This Table is read with regulation 3(b), which defines a sponsoring authority as an authority specified in the Table, and regulation 5(4), which requires the approved list of items from the concerned sponsoring authority with the registration application. Heading 98.01 is named in the regulations; the duty rate is not stated in the Table and is not given here. For the registration steps, see our article on regulations 5 to 7. Importers confirming which authority applies to their project can use our compliance advisory service.

The Table as printed

SerialPlant or projectSponsoring authority
1All plants and projects under SSI UnitsDirector of Industries of the concerned State
2All Power Plants and Transmission Projects, other than solar power plants or solar power projects: (a) to (i) belowThe corporation named against each
2(a)National Thermal Power Corporation Ltd.National Thermal Power Corporation Ltd.
2(b)Tehri Hydro Development Corporation Ltd.Tehri Hydro Development Corporation Limited
2(c)Nathpa Jhakri Power Corporation Ltd.Nathpa Jhakri Power Corporation Limited
2(d)North Eastern Electric Power Corporation Ltd.North Eastern Electric Power Corporation Limited
2(e)National Hydroelectric Power Corporation Ltd.National Hydroelectric Power Corporation Limited
2(f)Bhakra Beas Management BoardBhakra Beas Management Board
2(g)Central Power Research InstituteCentral Power Research Institute
2(h)National Power Training InstituteNational Power Training Institute
2(i)Power Grid Corporation of India Ltd.Power Grid Corporation of India Ltd.
3Power Plants and Transmission Projects, other than solar power plants or solar power projects and other than those at serial 2Secretary to the State Government or Union Territory concerned dealing with the subject of power or electricity
3ADrinking Water Supply Projects for supply of water for human or animal consumptionCollector, District Magistrate or Deputy Commissioner of the District in which the project is located
3BAerial Passenger Ropeway ProjectJoint Secretary to the Government of India in the Ministry of Tourism, or the Secretary to a State Government dealing with the subject of tourism
3CWater Supply ProjectsCollector, District Magistrate or Deputy Commissioner of the District in which the project is located
3DPipeline projects for the transportation of crude oil, petroleum products or natural gasMinistry of Petroleum and Natural Gas
3E(a) Digital cinema development projects; (b) Digital head end projectMinistry of Information and Broadcasting
3FMetro Rail or Monorail project for urban public transportConcerned State Government
3FFAll Metro Rail or Monorail projects under items (i) to (xiv) belowThe officer named against each item
3FFFHigh Speed Rail ProjectsNational High Speed Rail Corporation Limited
3GProject for installation of mechanized handling systems and pallet racking systems in mandis and warehouses for food grains, sugar and horticulture produceMinistry of Agriculture
3HCold storage, cold room (including for farm level pre-cooling), cold chain including pre-cooling unit, packhouses, sorting and grading lines and ripening chambers, or industrial projects for preservation, storage or processing of agricultural, apiary, horticultural, dairy, poultry, aquatic and marine produce and meatMinistry of Food Processing Industries
3-IGreen house set up for protected cultivation of horticulture and floriculture produceMinistry of Agriculture
4Any other Plant and Project, other than solar power plant or solar power projectConcerned Administrative Ministry or Department

Serial 3FF: the metro rail projects

ItemProjectSponsoring authority as printed
(i)Kolkata Metro Rail ProjectManaging Director or Director (Rolling Stock and Technical) of Kolkata Metro Rail Corporation Ltd (KMRCL)
(ii)Delhi Metro Rail Project, Delhi and NCRManaging Director or Director (Electrical) or Director (Finance), Delhi Metro Rail Corporation (DMRC)
(iii)Bangalore Metro Rail ProjectManaging Director or Director (Rolling Stock, Signaling and Electrical) of Bangalore Metro Rail Corporation Ltd (BMRCL)
(iv)Chennai Metro Rail ProjectManaging Director or Director (Systems and Operations) of Chennai Metro Rail Limited
(v)Kochi Metro Rail ProjectManaging Director or Director (Systems), Kochi Metro Rail Ltd.
(vi)Mumbai Metro Rail ProjectManaging Director or Director (Systems), Mumbai Metro Rail Corporation Limited
(vii)Lucknow Metro Rail ProjectManaging Director or Director (Rolling Stock and Systems), Lucknow Metro Rail Corporation Ltd (LMRC)
(viii)Ahmedabad Metro Rail ProjectManaging Director of Metro-Link Express for Gandhi Nagar and Ahmedabad (MEGA) Company Ltd.
(ix)Nagpur Metro Rail ProjectManaging Director of Maharashtra Metro Rail Corporation Ltd.
(x)Pune Metro Rail ProjectManaging Director of Maharashtra Metro Rail Corporation Ltd.
(xi)Noida Metro Rail ProjectManaging Director of Noida Metro Rail Corporation (NMRC)
(xii)Bhopal Metro Rail ProjectManaging Director, Madhya Pradesh Metro Rail Corporation Limited (MPMRCL)
(xiii)Indore Metro Rail ProjectManaging Director, Madhya Pradesh Metro Rail Corporation Limited (MPMRCL)
(xiv)Jaipur Metro ProjectsManaging Director or Director (Project), Rajasthan Metro Rail Corporation Limited (RMRCL)

The two recent changes

Solar power carve-out (from 2 February 2023). Notification No. 07/2023-Customs, dated 1 February 2023, amended serial 4 so that it reads "Any other Plant and Project, other than solar power plant or solar power project". Serials 2 and 3 already exclude solar power plants and solar power projects (those words were substituted from 20 October 2022 by Notification No. 54/2022). The result is that a solar power plant or project is not within any of serials 2, 3 or 4 as they now read. The Table does not say what route, if any, applies to solar plants; the text is silent.

Jaipur Metro (from 29 November 2025). Notification No. 49/2025-Customs, dated 28 November 2025, in force from 29 November 2025, inserted item (xiv) in serial 3FF after item (xiii): Jaipur Metro Projects, with the Managing Director or Director (Project) of Rajasthan Metro Rail Corporation Limited as sponsoring authority.

How to use the Table

  1. Find the row that describes your plant or project; if no specific row fits, serial 4 applies, unless the project is a solar power plant or project.
  2. Identify the sponsoring authority against it.
  3. Obtain that authority's clearance and approved list of items, which go with the registration application under regulation 5(4).
  4. Apply for registration of the contract before clearance, as regulation 4 requires.

Serial 3FF is a specific entry for metro rail and monorail projects that names the project and the officer, while serial 3F is the general entry for metro rail or monorail projects for urban public transport with the concerned State Government as sponsor. The Table does not explain how the two interact; read the specific project name first.

A worked example

RajPath Rail Engineering has a contract to supply rolling stock components to the Jaipur Metro. Under the Table as amended from 29 November 2025, it looks at serial 3FF, item (xiv), and approaches the Managing Director or Director (Project) of Rajasthan Metro Rail Corporation Limited for the approved list of items. It then registers its contract at the Custom House before the first consignment is cleared. A rooftop solar developer, by contrast, cannot use serial 4 for its project, as the words "other than solar power plant or solar power project" now exclude it.

Need help finding the right sponsoring authority?

If your project is not clearly in one row of the Table, or you are unsure which authority should issue the approved list of items, our compliance advisory team can read the Table with you and plan the registration.

Key takeaways

  • The Table pairs each plant or project with a sponsoring authority, whose approved list of items goes with the registration application.
  • Serial 4, "Any other Plant and Project", excludes solar power plants and projects from 2 February 2023.
  • Serials 2 and 3 also exclude solar power plants and projects.
  • Item (xiv) of serial 3FF, Jaipur Metro Projects, applies from 29 November 2025, with Rajasthan Metro Rail Corporation Limited as the authority.
  • The Table names no duty rate.

Read next

Disclaimer: Based on the customs regulations named above as published on the CBIC Tax Information Portal or in the Gazette and, for sets amended since 2023, the amending notifications (read through a TaxClue consolidated reading text; no official consolidated text exists), as consulted on 3 October 2026. Later notifications, fees and the Customs Act, 1962 provisions referred to should be checked. This article is general information, not legal advice; check the official text before acting.

Quick recapKey facts & short answers

Key Facts About Table

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

What is a sponsoring authority?

An authority specified in the Table annexed to the regulations (regulation 3(b)). The importer takes the approved list of items from it for the registration application.

What changed in serial 4 in 2023?

From 2 February 2023, "Any other Plant and Project" reads "Any other Plant and Project, other than solar power plant or solar power project".

Every shipment tells its story in documents; make sure they all tell the same one.

— TaxClue Trade & FEMA Desk

Table: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related Services & Guides

Was this article helpful?
About the author
Vikas Sharma Tax & Compliance Expert at TaxClue

Experienced in company registration, GST, trademark, and compliance. Helping Indian businesses stay compliant.

Updated: Live

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case — always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 6 questions readers ask most on this topic.

An authority specified in the Table annexed to the regulations (regulation 3(b)). The importer takes the approved list of items from it for the registration application.

From 2 February 2023, "Any other Plant and Project" reads "Any other Plant and Project, other than solar power plant or solar power project".

No. Serials 2 and 3 also read "other than solar power plants or solar power projects".

The Managing Director or Director (Project), Rajasthan Metro Rail Corporation Limited, under item (xiv) of serial 3FF, in force from 29 November 2025.

Serial 1 names the Director of Industries of the concerned State as sponsoring authority for all plants and projects under SSI Units.

No. It lists the projects and sponsoring authorities only.