15 OCTPF & ESI · Contributions · Sep 2026in 2 days 20 OCTGSTR-3B · Summary return · Sep 2026in 7 days 21 OCTTax Audit Report · Form 3CA/3CB · AY 2026-27 · extended from 30 Sepin 8 days 30 OCTAOC-4 · Financial statements · FY 2025-26in 17 days 7 NOVTDS / TCS deposit · Deducted in Oct 2026in 25 days 11 NOVGSTR-1 · Outward supplies · Oct 2026in 29 days 21 NOVITR filing · Audit cases · AY 2026-27 · extended from 31 Octin 39 days 29 NOVMGT-7 / 7A · Annual return · FY 2025-26in 47 days
All due dates
RERA Live

Section 61 of the Real Estate (Regulation and Development) Act, 2016: Penalty for Contravention of Other Provisions

A promoter who contravenes any other provisions of the Act, other than that provided under section 3 or section 4, or the rules or regulations made thereunder, is liable to a...

Published
Updated
Reading time
6 min
Views
8
Questions
6 answered
  • Expert Reviewed
  • High Complexity
Topic
RERA
Published
October 1, 2026
Last updated
Oct 13, 2026
Reading time
6 min
0:00
Last updated: October 2026Verified against: Government sources

Section 61 is the catch-all penalty for promoters. Anything a promoter does in breach of the Act, other than sections 3 and 4 which have their own penalties, and anything in breach of the rules or regulations made under it, is covered. The penalty may extend up to five per cent of the estimated cost of the real estate project, as determined by the Authority. For a promoter facing a notice on a missed duty, our legal dispute resolution team can help prepare the reply.

Section 61 at a glance

ItemWhat the section says
WhoAny promoter
TriggerContravenes any other provision of the Act (not sections 3 or 4), or the rules or regulations
PenaltyMay extend up to five per cent of the estimated cost of the real estate project
Who determinesThe Authority
ImprisonmentNone stated
Per-day elementNone stated

The text, in parts

"If any promoter contravenes any other provisions of this Act, other than that provided under section 3 or section 4, or the rules or regulations made thereunder, he shall be liable to a penalty which may extend up to five per cent. of the estimated cost of the real estate project as determined by the Authority."

What is carved out. Section 3 (registration of the project) is dealt with in section 59; section 4 (application for registration) is dealt with in section 60. See our post on section 59 and our article on section 60. Everything else is section 61.

What is brought in. Two things: "any other provisions of this Act" and "the rules or regulations made thereunder". The rules are made by each State (appropriate Government) and the regulations by the Authority, so the content of what a promoter must do beyond the Act differs by State; section 61 simply attaches the penalty to breaches of whichever rules and regulations apply.

What is capped. "May extend up to five per cent" of the "estimated cost of the real estate project". The text gives no minimum, no formula and no list of factors; the amount up to the ceiling is for the Authority to determine.

Which promoter duties does this reach?

The Act places many duties on promoters. The ones most commonly in question are the following, each of which has its own article in this series.

ProvisionSubjectOur article
11Functions and duties of the promoterSection 11
12False advertisement or prospectusSection 12
13No deposit or advance without agreement for saleSection 13
14Sanctioned plans and structural defectsSection 14
15Transfer of project to a third partySection 15
16InsuranceSection 16
17Transfer of titleSection 17
18Return of amount and compensationSection 18

The table is a guide to where section 61 may bite; whether a particular default is "a contravention" is for the Authority to decide on the facts. Section 61 does not name any of these sections.

Penalty and compensation are different things

Where a promoter's default hurts an allottee, two separate consequences can follow. The first is a penalty under section 61, decided by the Authority and measured against the project. The second is interest or compensation to the allottee, for example under sections 12, 14, 18 and 19, decided by the adjudicating officer under section 71; see our article on section 71. Section 61 does not say that a penalty displaces compensation, and nothing in it says that the two cannot both be ordered. The text is silent, so a promoter should not assume one excludes the other.

Compared with the orders-defiance penalties

Section 61 is about breaching the Act, rules or regulations. Failing to comply with an order of the Authority is a separate default under section 63, with a per-day structure; failing to comply with an order of the Appellate Tribunal is under section 64 and carries imprisonment. See our article on sections 63 and 64.

SectionDefaultPenalty ceilingImprisonment
61Contravenes other provisions of the Act, or the rules or regulationsFive per cent of estimated cost of the projectNone
63Does not comply with Authority's orders or directionsFive per cent of estimated cost, cumulatively, for every day of defaultNone
64Does not comply with Tribunal's orders, decisions or directionsTen per cent of estimated cost, cumulatively, for every dayUp to three years, or fine, or both

Illustration. A promoter with a project whose estimated cost is Rs 50 crore fails to keep a duty under the Act and the Authority finds a contravention under section 61. The penalty may extend up to Rs 2.5 crore, and could be less. If the promoter then ignores the Authority's order to remedy the default, section 63 may add a penalty for each day of default.

Process and appeal

The Authority determines the penalty after inquiry. An unpaid penalty is recoverable as arrears of land revenue under section 40(1). A promoter's appeal to the Appellate Tribunal needs a deposit of at least thirty per cent of the penalty, or a higher percentage the Tribunal fixes, under section 43(5). For companies, see section 69.

Need help with a compliance default?

Section 61 can be triggered by almost any lapse in a project, which makes records and timely correction important. We can review your compliance position and prepare a response to any notice. Speak to us about legal dispute resolution.

Key takeaways

  • Section 61 is the general penalty for promoters, outside sections 3 and 4.
  • It reaches contraventions of the Act and of the rules or regulations.
  • The penalty may extend up to five per cent of the estimated cost of the project, as determined by the Authority.
  • No imprisonment and no per-day amount are stated.
  • Penalty and compensation to the allottee are separate; the text does not make them exclusive.

Read next

Disclaimer: Based on the Real Estate (Regulation and Development) Act, 2016 as enacted, as consulted on 1 October 2026. Rules, forms, fees and procedures are made by each State and Union territory and its Real Estate Regulatory Authority and differ from State to State. This article is general information, not legal advice; check the official text and your State's rules before acting.

Quick recapKey facts & short answers

Key Facts About Section 61

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

What is the maximum penalty under section 61?

Up to five per cent of the estimated cost of the real estate project, as determined by the Authority.

Does section 61 cover breaches of State rules?

Yes, it covers "the rules or regulations made thereunder".

Mutate the records after purchase; ownership on paper should match ownership in the revenue books.

— TaxClue Property Desk

Section 61: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related Services & Guides

Was this article helpful?
About the author
13,350 articles
Vikas Sharma Verified expert Tax & Compliance Expert

Experienced in company registration, GST, trademark, and compliance. Helping Indian businesses stay compliant.

Last reviewed: Live

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case — always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 6 questions readers ask most on this topic.

Up to five per cent of the estimated cost of the real estate project, as determined by the Authority.

Yes, it covers "the rules or regulations made thereunder".

No. Only a penalty is stated.

Sections 3 and 4, which are dealt with in sections 59 and 60.

Compensation under sections 12, 14, 18 and 19 is decided by the adjudicating officer under section 71; section 61 does not exclude it.

The Authority.