The Customs (On-Arrival Movement for Storage and Clearance at Authorised Importer Premises) Regulations, 2025 are not yet in force. Regulation 1(2) says they will come into force from the date to be notified, and no commencement notification was found up to 3 October 2026. Once in force, regulations 1 to 6 will let a qualifying importer apply to have imported goods moved from the port to its own designated place inside a licensed warehouse and cleared or removed from there. This article explains what the regulations provide, so that importers can prepare.
Not yet in force. Once in force, the regulations will apply only to importers who are AEO Tier II or Tier III, with a designated place inside a warehouse licensed under section 58 or 58A that also has section 65 permission, and whose resultant goods fall in headings 8517 to 8548. The importer will apply to the Commissioner, declare its intent in the bill of entry, and the Customs Automated System will grant an automated permission for storage on arrival, unless one of three holds applies.
Position of the text: as amended up to 3 October 2026, no amendment found; the text is as made by Notification No. 11/2025-Customs (N.T.) dated 17 February 2025, and it is not yet in force: commencement is from a date to be notified, and no commencement notification was found up to 3 October 2026. Later notifications should be checked. This is the text as published.
The regulations are made under section 157 read with section 143AA of the Customs Act, 1962 for facilitation of trade. The Act's provisions are covered in sections 143 to 143AA of the Customs Act, 1962. Importers who qualify as AEOs and run bonded warehouses can take advice from our compliance advisory team on preparing for the facility. The obligations that will follow permission are in our article on regulations 7 to 11.
Regulation 1: title and commencement (not yet in force)
Regulation 1(1) gives the short title. Regulation 1(2) says the regulations will come into force with effect from the date to be notified. Until a notification fixes that date, nothing in these regulations can be relied on as operational law.
Regulation 2: definitions
| Term | Meaning (once in force) |
|---|---|
| Authorised Importer | The importer authorised under regulation 4 |
| Authorised Importer Premises | The designated place authorised for storage of imported goods before clearance or removal under regulation 4 |
| Clearance at Authorised Importer Premises | Includes movement of the Authorised Importer's imported goods from the port to the Authorised Importer Premises, storage, examination, clearance or removal |
| Form | The Form annexed to the regulations |
Undefined words will have the meaning in the Act or notifications under it.
Regulation 3: who the regulations will apply to
The regulations will apply to two things at once: the importer and the goods.
The importer (clause (a)). It must satisfy all four conditions:
- it is recognised as an Authorised Economic Operator under Tier II or Tier III status;
- it has a designated place demarcated within an already licensed warehouse under section 58 or section 58A of the Act;
- the licensed bonded warehouse where the designated place is demarcated has permission under section 65 of the Act; and
- the resultant goods pertain to goods classified under headings 8517 to 8548.
The goods (clause (b)). Only imported goods for which no order has been made under section 47 or section 60 of the Act and in respect of which the importer intends to avail clearance at Authorised Importer Premises.
A Tier I AEO, a non-AEO, a warehouse without section 65 permission or an importer whose resultant goods are outside headings 8517 to 8548 will therefore not qualify. The manufacturing-in-warehouse scheme that section 65 permission refers to is explained in our post on bonded manufacturing under section 65.
Regulation 4: registration
Regulation 4(1). Subject to regulation 3, an importer who intends to avail the facility will make an application, in the Form annexed, before the Commissioner of Customs having jurisdiction to issue the licence under section 58 or 58A.
Regulation 4(2). The Commissioner will get the Authorised Importer Premises verified within seven days.
Regulation 4(3). On the basis of that verification, the Commissioner will decide the application within seven days and communicate the decision to the applicant. The proviso says that where the verification or information provided is insufficient to decide the application, the Commissioner may give the importer a further period of fifteen days to make it sufficient.
A note says any reference to the Commissioner includes the Principal Commissioner.
The Form. The application Form asks for the importer's name, IEC and registered address; the AEO number, status and validity; the warehouse code, address and the facility and equipment available; the resultant goods to be made, with description, four-digit tariff heading and sector; and the name, designation and contact details of a nodal senior management person.
| Step | Time limit as printed |
|---|---|
| Verification of the premises | Within seven days |
| Decision on the application | Within seven days of verification |
| Extra time where information is insufficient | A further fifteen days, at the Commissioner's option |
Regulation 5: declaration of intent
Once authorised, the Authorised Importer will declare its intent in the bill of entry under section 46 of the Act, along with the details of the Authorised Importer Premises. The facility is therefore claimed shipment by shipment, in the bill of entry.
Regulation 6: automated permission
Regulation 6(1). On arrival of the goods and completion of the electronic process for the goods covered in the bill of entry, including reconciliation with the arrival manifest, the Customs Automated System will grant an automated permission for storage at the Authorised Importer Premises. The proviso says the permission will not be available where:
- (a) the goods are selected for scanning and found suspicious after scanning;
- (b) a no-objection from any Government agency is pending; or
- (c) the release is kept on hold on specific intelligence.
Regulation 6(2). The decision on the permission will be made available to the importer electronically.
A worked example (for illustration, once the regulations are in force)
Nova Circuits, an electronics manufacturer, is an AEO Tier III importer with a designated place inside its bonded warehouse, which holds section 65 permission, and its resultant goods are classified under heading 8517. Once the regulations come into force, Nova will apply to the Commissioner in the annexed Form; the premises will be verified within seven days and the application decided within seven days after that. For each shipment, Nova will declare in the bill of entry that it wants clearance at its premises. When the goods arrive and the manifest is reconciled, the system will grant the permission, unless the container is flagged after scanning, a Government agency no-objection is pending or an intelligence hold applies.
What to prepare now
- Check whether your AEO status is Tier II or Tier III, and whether the warehouse has section 58 or 58A licence and section 65 permission.
- Check the tariff headings of resultant goods against 8517 to 8548.
- Wait for the notification fixing the commencement date before acting on the facility.
Need help preparing for the facility?
If your company is an AEO with a bonded warehouse and wants to assess whether it will qualify once the regulations are notified, our compliance advisory team can check each condition in regulation 3 against your set-up.
Key takeaways
- The regulations are not yet in force; commencement is from a date to be notified, and none was found up to 3 October 2026.
- Once in force, they will apply to AEO Tier II or Tier III importers with a designated place in a section 58 or 58A warehouse that has section 65 permission, for resultant goods in headings 8517 to 8548.
- The Commissioner will verify within seven days and decide within seven days, with up to fifteen further days if information is insufficient.
- The intent will be declared in the bill of entry, and the Customs Automated System will grant permission on arrival unless a hold applies.
Read next
- Regulations 7-11 of the Customs (On-Arrival Movement for Storage and Clearance at Authorised Importer Premises) Regulations, 2025: obligations
- Sections 143-143AA of the Customs Act, 1962: bonds for import or export and simplified procedures
- Customs bonded manufacturing: section 65 MOOWR scheme
Disclaimer: Based on the customs regulations named above as published on the CBIC Tax Information Portal or in the Gazette and, for sets amended since 2023, the amending notifications (read through a TaxClue consolidated reading text; no official consolidated text exists), as consulted on 3 October 2026. Later notifications, fees and the Customs Act, 1962 provisions referred to should be checked. This article is general information, not legal advice; check the official text before acting.