30 JUNIEC update · Annual confirmation on DGFT (Apr–Jun)in 243 days 30 OCTAOC-4 · Financial statements · FY 2025-26due today 7 NOVTDS / TCS deposit · Deducted in Oct 2026in 8 days 11 NOVGSTR-1 · Outward supplies · Oct 2026in 12 days 15 NOVPF & ESI · Contributions · Oct 2026in 16 days 20 NOVGSTR-3B · Summary return · Oct 2026in 21 days 21 NOVITR filing · Audit cases · AY 2026-27 · extended from 31 Octin 22 days 29 NOVMGT-7 / 7A · Annual return · FY 2025-26in 30 days
All due dates

Interest Equalisation Scheme for Exporters

How the Interest Equalisation Scheme worked — eligible exporters, covered tariff lines, the rate of benefit, per-IEC caps and the claim mechanism through banks — and why its...

Published
Updated
Reading time
5 min
Questions
6 answered
  • High Complexity
Topic
Customs
Published
September 5, 2026
Last updated
Sep 5, 2026
Reading time
5 min
0:00
Last updated: September 2026Verified against: Government sources

What the Scheme Did

Indian exporters compete against suppliers in economies where working capital is structurally cheaper. The Interest Equalisation Scheme addressed that directly: rather than granting a cash incentive linked to export value, it reduced the cost of the credit itself.

Mechanically it is simple. The bank charges the exporter interest at a rate reduced by the notified percentage. The bank then claims that percentage from the Reserve Bank. The exporter applies for nothing; the benefit appears as a lower rate on the facility.

Because the benefit is delivered through the banking channel, the practical questions for an exporter are eligibility, whether the bank has correctly identified the account as eligible, and whether the reduced rate has actually been applied.

The Scheme's Moving Parts

ElementWhat varied across notifications
Rate of equalisationDifferent percentages applied to different exporter categories at different times
Eligible exportersProgressively narrowed, with MSME manufacturer exporters retained longest
Covered tariff linesA specified list of tariff lines for some categories; all lines for others
Credit coveredRupee pre-shipment and post-shipment credit
Per-IEC annual capIntroduced and then reduced in later periods
Period of operationExtended repeatedly by notification, and allowed to lapse at points

That table is the important point about this scheme. Almost every parameter has changed at least once. A statement of "the rate" without a date is not usable, and advice given for one financial year has repeatedly been wrong for the next.

Checking the Position for Your Period

  1. Identify the borrowing period for which you are testing eligibility.
  2. Find the DGFT trade notice or notification and the RBI circular operative for that period. Both matter: DGFT sets scheme parameters, RBI instructs banks on operation and claims.
  3. Check your category — manufacturer exporter, merchant exporter, MSME status — against the eligibility in force then.
  4. Check your tariff lines against the covered list, if the notification applied one to your category.
  5. Check the cap per IEC for that year and how much of it you had already used.
  6. Confirm with your bank whether the account was flagged as eligible and the reduced rate applied.

Conditions That Consistently Applied

Across versions of the scheme, certain conditions recurred and are worth knowing:

  • Rupee credit only. The scheme applied to rupee export credit, not to foreign currency credit such as PCFC, which is priced off an international benchmark.
  • Valid IEC and, where applicable, valid Udyam registration for MSME categories.
  • Not available alongside certain other benefits for the same credit, to prevent double subsidy.
  • Not available where the account is irregular — the benefit does not run on overdue or restructured advances.
  • Bank-level certification and reporting, with the exporter's declaration on record.

Verifying Pass-Through

The most common practical failure is not denial but under-pass-through. An eligible exporter's account is not correctly flagged, and interest is charged at the full rate for months before anyone notices. To catch it:

  1. Take the notified benchmark and spread from your sanction letter for each period.
  2. Compute what the interest should have been, before and after the equalisation percentage.
  3. Compare against the interest actually debited on the statement, period by period.
  4. Where there is a gap, write to the bank citing the notification, your eligibility and the affected periods.
  5. Keep the correspondence; retrospective credits are usually given where eligibility is demonstrable, but they are not given automatically.

How to Plan Around Scheme Uncertainty

  • Do not price long-dated orders assuming the benefit. If the scheme lapses mid-order, the margin absorbs it.
  • Model your working capital cost both ways — with and without the benefit — when quoting.
  • Watch the cap. Where a per-IEC cap applies, the benefit is exhausted partway through the year for larger exporters, so the effective rate rises in the second half.
  • Compare against PCFC. The choice between rupee credit with a subvention and foreign currency credit without one changes as the scheme parameters and the two rate cycles move.
  • Keep MSME registration current if your eligibility depends on it. A lapsed Udyam registration silently ends the benefit.

Practical Tips

  • Ask your bank in writing, once a year, to confirm your eligibility status and the rate being applied under any subvention in force.
  • Retain the notification text applicable to each year with your loan file; reconstructing the position later is much harder.
  • Where you operate multiple IECs in a group, track the cap per IEC — it is not a group limit.
  • Treat any advice about "the current rate" that does not cite a dated notification as unreliable.

Related Services & Guides

Quick recapKey facts & short answers

Key Facts About Interest Equalisation Scheme

  • Applies in: All states across India, under the relevant central law.
  • Mode: Mostly online via the official government portal.
  • Typical timeline: Ranges from a few days to a few weeks depending on the case.
  • Non-compliance: May attract penalties, interest or late fees.
  • Expert help: TaxClue completes the entire process end to end for you.

What is the Interest Equalisation Scheme?

A government scheme under which a percentage of the interest on pre-shipment and post-shipment rupee export credit is borne by the government, so the exporter borrows at a reduced effective rate. Banks charge the reduced rate and claim reimbursement.

Is the scheme currently in force?

Its operation has been notified, extended, restricted and allowed to lapse at various points. Do not assume continuity — check the DGFT and RBI notification applicable to your borrowing period, and confirm with your bank whether the benefit is being passed through.

If a rule seems to have changed, check the date of what you are reading before you act on it.

— TaxClue Compliance Desk

Interest Equalisation Scheme: a key compliance topic in Indian tax and corporate law that businesses and individuals must understand to remain compliant.

Related Services & Guides

Was this article helpful?
About the author
Vikas Sharma Tax & Compliance Expert at TaxClue

Experienced in company registration, GST, trademark, and compliance. Helping Indian businesses stay compliant.

Updated:

Disclaimer: This article is for general informational purposes only and does not constitute professional tax, legal or financial advice. Laws, rates and due dates change and can vary by individual case — always verify with the relevant government source (e.g. mca.gov.in, incometax.gov.in) or consult a qualified professional before acting. TaxClue accepts no liability for decisions taken based on this content.

People also ask

Questions, answered

Short, direct answers to the 6 questions readers ask most on this topic.

A government scheme under which a percentage of the interest on pre-shipment and post-shipment rupee export credit is borne by the government, so the exporter borrows at a reduced effective rate. Banks charge the reduced rate and claim reimbursement.

Its operation has been notified, extended, restricted and allowed to lapse at various points. Do not assume continuity — check the DGFT and RBI notification applicable to your borrowing period, and confirm with your bank whether the benefit is being passed through.

In its later form the scheme was progressively narrowed towards MSME manufacturer exporters, with a broader set of tariff lines available to other manufacturer exporters in earlier periods. Eligibility conditions changed with each extension.

The bank charges interest at the reduced rate and claims the equalisation amount from RBI. The exporter does not apply to government directly; the benefit appears as a lower rate on the facility, and should be verified against the sanction terms.

Yes, in later periods a cap per IEC per financial year applied, and the cap was reduced as the scheme was narrowed. Exporters exceeding the cap received no further benefit for that year.

Raise it with the bank in writing, referencing the notification and your eligibility. Reconcile interest actually charged against the notified reduced rate for the whole period, since under-pass-through is usually a systems mapping issue rather than a denial.