The corporate insolvency resolution process of Indian Soya Industries Private Limited is a case study in the successful resolution of an MSME despite an unusually large number of legal, commercial and administrative obstacles encountered over more than six years — from admission at the height of the pandemic to a leasehold termination issued two days after the CoC approved the resolution plan.
The corporate debtor
| Feature | Position |
|---|---|
| Business | Extraction of soya oil and manufacture of allied products — de-oiled cake and soya flour — for over four decades |
| Location | Two manufacturing units in Indore, Madhya Pradesh |
| Land | More than 10 acres of leasehold industrial land allotted by the District Industrial Centre (DIC), Government of Madhya Pradesh, in the mid-1980s |
| Capacity | Crushing capacity of approximately 600 metric tonnes per day; multi-product refinery storing and refining approximately 1,000 metric tonnes of edible oils; independent warehousing used for export of de-oiled cake |
| Creditor profile | A single financial creditor relationship of approximately 35 years' standing — described as unusually clean and long-standing for an account of this size |
| Employee dues | No outstanding statutory employee dues as on the commencement date |
Both units were originally located within an industrial zone. On account of the growth of Indore city, both came to be situated within municipal limits notwithstanding that original siting.
That single fact of urban expansion sits behind the most damaging obstacle the resolution plan later faced — the leasehold termination — because industrial land inside municipal limits has a value and a set of competing claims that industrial land on the periphery does not.
How the distress arose
Three events, in sequence:
- the demise of the principal promoter;
- incidents of fire; and
- a consequent, sustained working capital constraint.
The account was gradually classified as a non-performing asset, and the company was admitted into CIRP on 14 July 2020, on an application filed by an operational creditor, at the height of the COVID-19 pandemic.
Two points are worth noting for practitioners. The trigger was an operational creditor, not the bank with the 35-year relationship. And the distress was event-driven rather than a failure of the underlying business — which is precisely the profile the Code exists to rescue.
The obstacles the resolution plan had to survive
- A CIRP commenced during the pandemic, with a volatile commodity and limited residual liquidity.
- The CoC unable to conclude voting within the CIRP timeline because of COVID-19 disruption among its representatives, forcing the RP to file for liquidation as the Code mandates.
- Termination of the leasehold rights by the DIC two days after CoC approval, on the ground that the unit had been non-operational for more than two continuous years.
- Two departmental appeals rejected, the second by the same officer who had decided the first.
- A belated claim by the Commercial Tax Department more than 1,000 days after CoC approval.
- An intervention application by the unsuccessful third-ranked applicant seeking to revise its offer.
- Encroachment on part of the premises by a government agency using it to park seized vehicles.
Any one of these could have ended the process. The resolution plan survived all seven.
The outcome and the principles affirmed
The NCLT ultimately approved the resolution plan, reiterating three settled principles:
- resolution is the rule and liquidation the exception, and the doors of liquidation ought not to be opened where the resolution process can still be meaningfully pursued;
- the commercial wisdom of the CoC is not open to challenge before the Adjudicating Authority in the absence of a demonstrated legal infirmity in the process followed by the Resolution Professional; and
- a claimant who sleeps over its rights for an extended period cannot be permitted to reopen or delay a concluded resolution process.
The NCLT also permitted the Resolution Professional to pursue further remedies before the jurisdictional High Court on the leasehold dispute, notwithstanding the general restriction on institution of fresh legal proceedings without the leave of the Adjudicating Authority.
Why this case is worth studying
Most published CIRP case studies concern large corporate debtors where the contest is over value. This one is about an MSME where the contest was over whether the process could be kept alive at all — against a timeline expiry, a lessor, two appellate authorities, a tax department, a disappointed bidder and an encroaching agency.
The resolution plan that emerged was not the product of a superior valuation. It was the product of persistence across forums, documentation that held up years later, and a refusal to let procedural expiry substitute for a commercial outcome.
Compliance checklist
- Identify event-driven distress early — it is the most rescuable kind.
- Map leasehold and land tenure conditions at the outset, including non-operation clauses.
- Anticipate that a plant idle during CIRP may breach a lease condition even where no payment default exists.
- Treat timeline expiry as a risk to manage, not an automatic route to liquidation.
- Engage government departments proactively; they may not be familiar with the Code.
- Document CoC deliberations contemporaneously — they will be tested years later.
Common mistakes
- Assuming a clean banking relationship means a straightforward CIRP.
- Overlooking lease conditions triggered by non-operation.
- Treating liquidation as inevitable once the CIRP period expires.
- Relying on recollection rather than contemporaneous records.