Forms XV, XVI and XVII are the early-stage forms for the building workers' cess. Form-XV informs the assessing officer that a building or construction work is starting or changing; Form-XVI is the self-assessment of cess, certified by a chartered engineer; and Form-XVII reports a stoppage or reduction of work and can lead to a refund.
Every employer furnishes Form-XV to the assessing officer within sixty days of starting work or paying cess, and updates it within thirty days of a change. Cess is paid in advance on a self-assessment in Form-XVI, certified by a chartered engineer. On stoppage or reduction, Form-XVII goes to the assessing officer within sixty days; it is also the route to refund of excess advance cess (rule 41).
Where the forms come from
These forms are used under rule 41 of the Central Rules ("Collection and refund of cess"), which implements the cess levied under section 100(1) of the Code. See rule 41 and sections 100 to 102. The Central Rules apply where the Central Government is the appropriate Government; State-sphere employers follow State rules, and the cess is paid to the State Building Workers' Welfare Board. The completion return and appeal forms are in Forms XVIII and XIX. For help with cess compliance on a project, our labour law compliance team can assist.
| Form | Rule | Who | When | Purpose |
|---|---|---|---|---|
| XV | 41(1)(a), (b) | Employer | Within 60 days of commencement of work or payment of cess; changes within 30 days | Information on commencement or modification |
| XVI | 41(2)(b) | Employer | In advance, at approval or before commencement | Self-assessment of cess |
| XVII | 41(2)(e), 41(5) | Employer | Within 60 days of stoppage or reduction | Notice of stoppage or reduction; basis for refund |
Form-XV: commencement or modification
Filing rule. Every employer furnishes the information in Form-XV to the assessing officer within sixty days from the date of commencement of work or payment of cess, as the case may be (rule 41(1)(a)). Any change or modification is communicated in Form-XV, with details, immediately but not later than thirty days from the change (rule 41(1)(b)).
Content as printed. Name and permanent address of the establishment; employer's name and address details; name and location of the place where the building or other construction is to be carried on; name, designation, address and contact details of the authorised person; correspondence address; nature of the proposed work; date of commencement (if started); approximate duration; and details of any change or modification. A declaration states that the building or construction work, with its registration number and date, is likely to commence or modify from a stated date, signed and sealed by the employer with name, date, place, mobile number and email (if any).
Form-XVI: self-assessment of cess
Rule. Cess under section 100(1) is paid in advance, on the employer's self-assessment certified by a chartered engineer, at the time of approval or before commencement of work (rule 41(2)(a)). For the cost of construction, the employer uses the uniform rates specified by the State PWD, the CPWD or another applicable schedule of rates, or, where RERA applies, the rates in the return or document submitted to the Real Estate Regulatory Authority, for the year in which work commenced, in Form-XVI (rule 41(2)(b)).
Related rules.
- Where a local authority's approval is required, each application must carry proof of online payment in favour of the State Building Workers' Welfare Board of the cess on the self-assessment certified by the chartered engineer (41(2)(c)). If the project is expected to exceed one year, the advance may be for the cess on the cost self-assessed to be incurred in the first year, with later payments as per clause (b).
- For Government or public sector undertaking work, the cess is deducted at source from bills at the notified rates and deposited with the Board within thirty days of deduction (41(2)(d)).
- Advance cess is adjusted in the final assessment order (41(2)(g)).
Content of Form-XVI as printed. The same identification and project particulars as Form-XV, plus: total proposed area; total estimated cost of construction based on PWD, CPWD, RERA or other rates, with original documents as per rule 41; estimated cost as certified by a chartered engineer; provisional cess as a percentage of estimated cost as notified by the Central Government, with the total in rupees; advance cess paid (with details) or deduction at source; cess paid year-wise (first, second, third year) where duration exceeds one year; and the total cess paid (advance plus yearly). There is a two-part declaration: particulars are true and nothing is concealed or misrepresented; and the employer is aware of the penal provisions of the Code, and any incorrect self-assessment, concealment or under-calculation can attract punitive action. It is signed, sealed, and certified by the chartered engineer with registration number and stamp.
The rule does not state the cess percentage; it refers to the percentage notified by the Central Government. Check the notification in force.
Form-XVII: stoppage or reduction, and refund
Filing rule. If there is any stoppage or reduction of building or other construction work, the employer furnishes Form-XVII to the assessing officer within sixty days of the stoppage or reduction (rule 41(2)(e)).
Refund route. Where advance cess has been paid and the employer withdraws from or forecloses the work, modifies the plan so that the cost falls, or is forced to call off completion, he may seek refund of excess advance cess by submitting Form-XVII (rule 41(5)(a)). The assessing officer scrutinises it and makes an assessment order within thirty days; the State Building Workers' Welfare Board then refunds through electronic payment within thirty days of receiving the endorsement (41(5)(b) to (d)).
Content as printed. Establishment name, registration number and address; date of commencement and approximate proposed period; date of stoppage or reduction; total estimated cost; total incurred cost; total cess payable (percentage of incurred cost as notified); advance cess paid or deducted at source; year-wise cess paid; total paid; outstanding cess (payable less paid) with proof of payment; overpaid cess; bank account details for refund in case of overpayment; and remarks. The same two-part declaration and chartered engineer certification apply.
Example. A developer pays advance cess on an estimated cost, then scales down the project. Within sixty days of the reduction it files Form-XVII showing the incurred cost, cess payable, advance paid, and the overpayment with its bank account. The assessing officer assesses within thirty days, and the Board refunds within thirty days of the endorsement.
Need help with cess forms on a project?
Choosing the right rate schedule, getting the chartered engineer's certificate and meeting the sixty-day and thirty-day dates are where builders slip. Our labour law compliance team can help you prepare and track these filings.
Key takeaways
- Form-XV: within sixty days of commencement or cess payment; changes within thirty days.
- Form-XVI: advance self-assessment certified by a chartered engineer using PWD, CPWD, RERA or other applicable rates.
- Form-XVII: within sixty days of stoppage or reduction; route to refund of excess advance cess.
- The cess percentage is the one notified by the Central Government; it is not in the rule.
- State-sphere employers follow State rules.
Read next
- Rule 41: collection and refund of cess
- Forms XVIII and XIX: cess return and appeal
- Sections 103 to 105: self-assessment, penalty and appeal on cess
- Building and construction: BOCW Act and the labour codes
Disclaimer: Based on the Code on Social Security, 2020 (as enacted) and, where noted, the Code on Social Security (Central) Rules, 2026 (G.S.R. 344(E), 8 May 2026), as on 30 September 2026. The Code is in force from 21 November 2025; some provisions may be notified later, and State Governments make their own rules for establishments where the State is the appropriate Government. Verify the current position before acting.