CoC Code of Conduct explained: this guide covers what it means, who it applies to, the step-by-step process, documents required, fees, due dates and penalties in India — so you can stay compliant with confidence and avoid costly mistakes.
The IBC (Amendment) Act, 2026 introduces a statutory Code of Conduct for Committee of Creditors members along with mandatory CoC decision timelines. It is the first time the Code imposes accountability on the creditor side of the process, and it responds to CoCs taking five to eight months in several cases to approve or reject a resolution plan.
The finding behind the reform
ICAI's assessment is direct: "one of the most cited causes of delay in CIRP is not judicial backlog but CoC inaction". CoCs have in several cases taken five to eight months to approve or reject resolution plans, creating uncertainty for resolution applicants and eroding asset value during the interim period.
That reframes the timeline debate. The 330-day outer limit has been widely discussed as a judicial capacity problem. A material part of it is a creditor decision-making problem — and until 2026 the Code had no answer to it, because every accountability mechanism in it pointed at the resolution professional.
The asymmetry the amendment corrects
| Participant | Accountability before 2026 | After the amendment |
|---|---|---|
| Resolution professional | Compliance timelines, IBBI regulations, disciplinary process | Unchanged, plus section 47 exposure on avoidance transactions |
| Adjudicating Authority | None specific | 14-day admission, 30-day orders, comply or explain |
| NCLAT | None specific | Three months to dispose of appeals |
| Committee of Creditors | None | Code of Conduct and mandatory decision timelines |
ICAI's framing is that the CoC Code of Conduct mirrors the accountability already imposed on RPs through compliance timelines and IBBI regulations. The amendment does not add a new kind of obligation; it extends an existing one to the participant it had never reached.
Three layers of enforcement
- IBBI. ICAI is clear that effective implementation will require IBBI to issue granular guidelines. A code of conduct at statute level without operational detail is not enforceable in practice.
- NCLTs. Tribunals will need to be empowered to enforce the Code of Conduct — the mechanism for a breach has to sit somewhere.
- RBI. The RBI is also expected to reinforce CoC discipline through its own monitoring frameworks for banking institutions during CIRP. Since banks dominate most CoCs, prudential supervision is a faster lever than insolvency-side enforcement.
The honest position for now: the obligation exists in the Code, and the machinery to enforce it is being built.
What it gives the resolution professional
This is the practical change that arrives immediately, before any guideline issues. The Code of Conduct creates a formal framework for documenting CoC delays and, if necessary, approaching the Adjudicating Authority when CoC inaction is prejudicing the process.
Previously an RP facing an unresponsive committee had a professional problem and no remedy — raising it risked the relationship with the very creditors who could replace the RP, and there was no standard against which the delay could be measured. Now there is a standard, and a documented record against it is the basis for an application.
How to operate it in practice
- Minute the decision points. When a matter was placed before the CoC, what was sought, and what was decided or deferred.
- Record deferrals with reasons given by the committee, or their absence.
- Quantify the prejudice. Asset value erosion, expiry of a bid validity, loss of a customer contract — delay has to be tied to consequence.
- Escalate within the CoC first, in writing.
- Approach the Adjudicating Authority where inaction is prejudicing the process, with the documented record.
What the CoC member should do
- Set internal decision timelines that fit the statutory ones, including the internal credit approvals that actually cause most bank-side delay.
- Delegate authority to the representative attending the CoC where possible; a representative who must revert for every decision is the delay.
- Record the commercial reasoning for a rejection or a deferral — the Code of Conduct is a conduct standard, not a requirement to approve.
- Watch the RBI monitoring framework if the member is a regulated institution.
Compliance checklist
- Maintain a CoC decision register from the first meeting.
- Record what was sought, when, and what was decided — including deferrals.
- Tie any delay to quantified prejudice.
- Escalate in writing within the CoC before approaching the tribunal.
- For creditor institutions, align internal credit approval timelines with the CoC's statutory ones.
- Track IBBI guidelines as they issue; the operative detail is not in the Act.
Common mistakes
- Treating the Code of Conduct as a duty to approve plans. It governs conduct and timeliness, not commercial outcome.
- Failing to minute deferrals — an undocumented delay cannot be escalated.
- Escalating without quantified prejudice.
- Assuming it is enforceable today without IBBI guidelines.
- Sending a CoC representative with no delegated authority.